Commissioning

7.5 Testing Readiness for Operation

7.5

Testing Readiness for Operation

By carrying out the points in
nets, additional wiring and communication connections are necessary.
Siemens recommends the following procedure in this order:
Testing Binary Inputs and Outputs
Check that the connection from the output of the testing equipment to the device is correct and the binary
inputs and outputs are connected correctly.
Testing Current Inputs
Using multi-phase test equipment, apply the corresponding test quantities and check the results.
88
7.3 Initial
Startup. The device is ready for operation. If devices are built into cabi-
Reyrolle, Operating, Manual
C53000-B7040-C101-1, Edition 08.2020