Sliding Cabinets - Huawei FusionDC1000A Maintenance Manual

Prefabricated all-in-one data center
Hide thumbs Also See for FusionDC1000A:
Table of Contents

Advertisement

FusionDC1000A Prefabricated All-in-One Data
Center
Maintenance Guide (IT Scenario)
Figure 3-6 Repainting using a painting gun
----End
Follow-up Procedure
Check whether the surface meets the requirement after repainting.

3.2 Sliding Cabinets

Context
Procedure
Step 1 Remove the bolts securing the cabinet sliding base fasteners using an adjustable
wrench, and remove the fasteners.
Issue 01 (2021-04-20)
If the maintenance space on the rear door of the integrated UPS in the N+X
scenario is insufficient, slide the cabinet to expand the maintenance space.
If the maintenance space on the rear door of an IT cabinet is insufficient in
the N+X or 2N scenario, slide the cabinet to expand the maintenance space.
Figure 3-7 Sliding direction and distance
(1) IT cabinet
Copyright © Huawei Technologies Co., Ltd.
3 Routine Maintenance
(2) UPS cabinet
24