Commissioning

6.1

Overview

Prerequisites
• The device has been installed.
• The device has been connected in accordance with the possible connection methods.
Steps for starting up the device
NOTICE
Irreparable device damage!
The wrong system connection can cause irreparable damage to the device, or can lead to
device failure or malfunctions.
• Before connecting the PAC1600, ensure that the local power supply conditions match
• Before starting up the PAC1600, check that all connections are correct.
Note
When performing an insulation test of the entire installation with AC or DC, you must
disconnect the device before starting the test.
1. Apply the measuring voltage. You can find more information on this in chapter Applying the
measuring voltage (Page 80).
2. Parameterize the device. You will find more information on this in the chapter
Parameterizing with powerconfig (Page 80).
3. Check the measured values.
7KT16 energy meter
Equipment Manual, 09/2020, 2514284147-04
the specifications on the type plate.