3. Install the ICC ground cable.
9

Installing Components

9.1
Installing Modules
M48300N1
PSU slot
PSU slots support the installation of the R4850G2 and
R4850N6.
The PSU, S4820G, and M48300N1 are installed in the
same way. The right figure shows how to install a PSU.
9.2
Installing a Router and Cables
1. Take out the tray.
Small tray Big tray
3. Reinstall the tray.
PSU slot
S4820G slot
When installing the
AR550C, AR550,
AR531, MA5621,
and MA5671, take
out the small tray.
When installing the
NE05E-SK, take
out the big tray.
Installing an AR550C Router
ICC ground cable
2. Install a router.
Installing an AR550 Router
6
NOTE
There are six types of
routers. The installation
of AR550 is used as an
example in steps 2 and 3.
MA5621 Router

Advertisement

loading

This manual is also suitable for:

Icc50