Figure 4-10 300 mm wide air conditioner base
Preparations
Tool: Phillips screwdriver
Material: air conditioner base (300 mm wide)
Document: base installation position diagram
Procedure
Step 1 Remove the four M6 screws from adjustable feet and set them aside.
Figure 4-11 Removing screws from adjustable feet
Step 2 Move the adjustable feet to the mounting holes on the base according to the depth of the air
conditioner.