Huawei FusionModule2000 Installation Manual page 35

Smart modular data center
Hide thumbs Also See for FusionModule2000:
Table of Contents

Advertisement

FusionModule2000 Smart Modular Data Center
Installation Guide
Step 2 Use a laser locator to mark two lines that are perpendicular to each other in a corner of the
planned installation position.
If no laser locator is available, use a right angle and thin rope to mark the two perpendicular lines.
Step 3 Place one corner of the marking-off template at the crossing point of the perpendicular lines to
determine the position for an end cabinet. Use a marker to mark the outline of the marking-off
template and the mounting holes for the cabinet on the floor.
If there is no need to secure the cabinet to the floor, mark only the outline of the marking-off
template.
Figure 3-2 Using a laser locator for positioning (single-row aisle containment)
(1) Marking-off template
----End
Issue 02 (2018-03-31)
(2) Laser locator
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.