Setting up the ISE
This section describes the steps required if the present configuration for the electrolyte
analyzer (ISE) is ever lost or requires modification.
Activating the ISE
1. Set the ELA switch in the power supply distribution chassis panel (on the back of the
analyzer) to the ON position.
2. At the Systems Specifications Settings window, set the Electrolyte option to Avail.
3. At the System Monitor window, set the electrolyte option to Operate.
Setting up ISE parameters
Perform any of the following tasks at the ISE Parameter settings window:
•
enter ISE parameters
•
Setup Calibration information
•
enter Normal value set
•
define wash and prime settings
•
define Rerun conditions
•
define Real time correction formula
1. At the Process Sequence window, set the processing and print order for electrolyte
tests (124 – 126).
2. At the QC Sample Definition window, add electrolyte tests to existing controls or
define additional controls for the tests.
3. At the Test Select window, select electrolyte tests to run on routine sample, controls,
and calibrators.
4. At the Sample Select window, select CTT position numbers that are set for
calibrators and controls.
5. At the Control Data Registration window, enter the applicable mean and standard
deviation from the product package insert.
ISE calibration
Verify that the CTT position setting at the ISE Parameter Settings window agrees with
the actual positions where you place the ISE standard on the CTT. Run the ISE
calibration using one of the following modes:
•
Start button (single point calibration)
•
ISE Operation window
Use the ISE Monitor window to review the calibration.