Simulating machining
5.7 Program control during simulation
5.7
Program control during simulation
5.7.1
Changing the feedrate
You can change the feedrate at any time during the simulation.
You can track the changes in the status line.
Note
If you are working with the "Simultaneous recording" function, the rotary switch (override) on
the control panel is used.
Procedure
Note
Toggling between "Override +" and "Override -"
134
1.
Simulation is started.
2.
Press the "Program control" softkey.
3.
Press the "Override +" or "Override -" softkey to increase or decrease
the feedrate by 5%.
- OR -
Press the "Override 100%" softkey to set the feedrate to the maximum
value.
- OR -
Press the "<<" softkey to return to the main screen and perform the
simulation with changed feedrate.
Press the <CTRL> and <Cursor down> or <Cursor up> keys to toggle
between the "Override +" and "Override -" softkeys.
Operating Manual, 03/2010, 6FC5398-6AP10-4BA0
Universal