Procedure For Commissioning The S7-1500 Automation System - Siemens SIMATIC S7-1500 System Manual

Automation system
Hide thumbs Also See for SIMATIC S7-1500:
Table of Contents

Advertisement

Commissioning

10.3 Procedure for commissioning the S7-1500 automation system

10.3
Procedure for commissioning the S7-1500 automation system
Requirements
● The CPU is in the "Factory settings" state or has been reset to factory settings (see
Resetting the CPU to factory settings (Page 218)).
● The SIMATIC memory card is as delivered or has been formatted.
Commissioning procedure
For the first commissioning of an S7-1500 automation system, we recommend the following
procedure:
Table 10- 1
Procedure for commissioning the SIMATIC S7-1500
Ste p
Pro cedure
1
Configure hardware in STEP 7 and perform pow-
er balance calculation (see also "Requirements:
CPU as bus device")
2
Create user program
3
Insert required modules
4
Wiring the assembly (system power supplies,
front connectors, etc.)
5
Insert SIMATIC memory card in the CPU
6
Switch on the CPU and system power supply
7
Check LEDs
8
Evaluate information on the CPU's display
9
Configure hardware in STEP 7 and download to
the CPU
10
Test inputs and outputs
164
Se e...
Section Power balance calculation (Page 45)
STEP 7 online help
Section Installation (Page 48)
Section Wiring (Page 63)
Section Removing/inserting a SIMATIC memory card on the
CPU (Page 165)
See section First power-on of the CPU (Page 167)
The meaning of the LEDs can be found in the manuals of
the modules.
Section CPU display (Page 193)
Online and diagnostics functions in STEP 7
The following functions are helpful: Monitoring and modify-
ing tags, testing with program status, forcing, modifying the
outputs in STOP mode. See section Test functions and fault
resolution (Page 225)
System Manual, 09/2016, A5E03461182-AD
Automation system

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Simatic et200mp

Table of Contents