Items To Be Checked Before A Test Run - Mitsubishi Electric PQHY-P72ZLMU-A Service Handbook

2016
Table of Contents

Advertisement

[ VIII Test Run Mode ]
VIII Test Run Mode

[1] Items to be checked before a Test Run

(1) Check for refrigerant leak and loose cables and connectors.
(2) When opening or closing the front panel of the control box, do not let it come into contact with any of the internal
components.
Before inspecting the inside of the control box, turn off the power, keep the unit off for at least 10 minutes, and confirm that
the capacitor voltage (inverter main circuit) has dropped to 20 VDC or less. (It takes about 10 minutes to discharge electricity
after the power supply is turned off.)
Control box houses high temperature parts. Be well careful even after turning off the power source.
(3) Measure the insulation resistance between the power supply terminal block and the ground with a 500V megger and
make sure it reads at least 1.0Mohm.
Do not operate the unit if the insulation resistance is below 1.0Mohm.
Do not apply megger voltage to the terminal block for transmission line. Doing so will damage the controller board.
The insulation resistance between the power supply terminal block and the ground could go down to close to 1Mohm imme-
diately after installation or when the power is kept off for an extended period of time because of the accumulation of refrigerant
in the compressor.
If insulation resistance reads at least 1Mohm, by turning on the main power and keeping it on for at least 12 hours, the refrig-
erant in the compressor will evaporate and the insulation resistance will go up.
Do not measure the insulation resistance of the terminal block for transmission line for the unit remote controller.
(4) When the power is turned on, the compressor is energized even while it is not operating.
Before turning on the power, disconnect all power supply wires from the compressor terminal block, and measure the insula-
tion resistance of the compressor.
Check the compressor for a ground fault. If the insulation resistance is 1.0 M or below, connect all power supply wires to
the compressor and turn on the power to the heat source unit. (The liquid refrigerant in the compressor will evaporate by en-
ergizing the compressor.)
(5) Check that the valve on the gas pipe and liquid pipe are fully open.
Securely tighten the cap.
(6) Check the phase sequence and the voltage of the power supply.
(7) [When a transmission booster is connected]
Turn on the transmission booster before turning on the heat source units.
If the heat source units are turned on first, the connection information for the refrigerant circuit may not be properly recognized.
In case the heat source units are turned on before the transmission booster is turned on, perform a power reset on the heat
source units after turning on the power booster.
(8) Turn on the main power to the unit at least 12 hours before test run to power the crankcase heater.
Insufficient powering time may result in compressor damage.
(9) When a power supply unit is connected to the transmission line for centralized control, perform a test run with the
power supply unit being energized. Leave the power jumper connector on CN41 as it is (factory setting).
HWE15150
- 177 -
GB

Advertisement

Table of Contents
loading

Table of Contents