Urodynamic interface
Final work steps
•
X
Perform a function test.
•
Attach all panels and housing components to the imaging system container.
Protective Conductor Test
NOTE
•
Perform the test in accordance with DIN VDE 0751, Part 1 (see ARTD Part 2,
ARTD-002.731.17).
- In the course of the test, the protective conductor resistance in the normal operating
state of the system must be measured from the protective conductor connection
clamp on the system side to all touchable conductive system parts.
Make sure that control cables or data cables between the components of the system
are not mistaken for a protective conductor connection.
The ground wire resistance must not exceed 0.2 ohms.
Document and assess the values determined in the repeat measurement, indicating the
measurement points.
Additionally, the measurement procedure and the measurement instrument used (type
designation and serial number) must be documented.
NOTE
Siemens AG
Medical Solutions
Perform the protective conductor test again after any repairs, in-
stallation of new components, or maintenance.
Document and assess the values determined in the repeat mea-
surement.
Evaluate the results by comparing the first measured value to the
corresponding values documented during previous maintenance
procedures or safety checks.
A sudden or unexpected increase in the measured values may in-
dicate a defect in the ground wire connections (ground wire or
contacts) - even if the limit value of 0.2 ohms is not exceeded.
SPL5-330.814.01.05.02
08.05
Page 17 of 18
CS PS 24
17
0
0
UROSKOP ACCESS