SUN2000-(100KTL, 110KTL, 115KTL)-M2
User Manual
Figure 5-14 AC terminal block dimensions
Procedure
Step 1 Prepare a cable.
Step 2 Remove rubber rings according to the cable diameter range.
Step 3 Secure the AC output power cable and PE cable.
Step 4 Install the support bar.
Step 5 Close the maintenance compartment door and tighten the two screws on the
door.
● Sufficient slack should be provided in the PE cable to ensure that the last cable
● The cable outer diameter can be measured using the ruler sticker in the
● Ensure that the cable jacket is in the maintenance compartment.
● Ensure that the AC output power cable is secured. Failing to do so may cause
● Before closing the maintenance compartment door, check that the cables are
● If a screw on the maintenance compartment door is lost, obtain the spare
Issue 02 (2022-06-30)
NO TICE
bearing the force is the PE cable when the AC output power cable bears pulling
force due to force majeure.
maintenance compartment.
the solar inverter to malfunction or damage to its terminal block by issues such
as overheating.
connected correctly and securely, and clean up the foreign matter from the
maintenance compartment.
screw from the fitting bag tied at the bottom of the maintenance
compartment.