BA1N Kinetic Energy Buffer
11.2.2
Preparing assembly
11.2.3
Mounting the BA1N energy storage device
11.3
Electrical connection
11.3.1
General
Record all measures taken in the commissioning log.
Prepare the mounting as follows:
1. Check the components for visible damage. Damaged components must
not be mounted.
2. Ensure that the dimensions and tolerances of the plant are suitable for
attachment (for details, see dimension drawing).
3. Ensure that the motor can be assembled in a clean, dry and dust-free
environment.
4. Have tools and auxiliary materials ready.
5. Check all components, mounting surfaces and threads for cleanliness.
Connect the energy storage device to the machine (observe tightening tor‐
ques). Check whether the connection is firm and accurate before carrying out
any further steps.
After proper mechanical assembly, carry out the electrical connection.
Use ready-made connection cables by Bosch Rexroth. These cables have
numerous benefits, e.g. extreme resilience and resistance as well as EMC-
compliant design.
Perform the electrical connection of the BA1N energy storage device accord‐
ing to the instructions in the chapter
Connection
techniques.
R911393264_Edition 01 Bosch Rexroth AG
55/73
Installation