System Connectors

Compare this illustration with your generator to familiarize yourself with the location of these connections.
D
A
A ‑ Fuse Block — Used to connect utility 240 VAC from
fuse block in ATS to the control board. Connect only
one wire per terminal.
B
B ‑ Two‑Pin Terminal Block — Used to connect start
signal wires to the control board. Connect only one
wire per terminal. Torque connector plug screws to 7
in-lb (7.9 Newton meter).
• For power output connection, use 300 volt, 167 °F-194 °F (75
°C-90 °C) wire. See chart on right for proper wire size.
• For Utility Circuit connection use #14 AWG minimum 300
volt, 167 °F-194 °F (75 °C-90 °C) wire.
• For transfer switch communication use #18 AWG twisted
pair conductors, no greater than 200 ft (60 m) in length,
300 volt, 167 °F-194 °F (75 °C-90 °C) wire.
C
B
REMOTE
START
CONTACT
80005289
A
GND
D ‑ Power Connection (Line 1, Line 2 and Line 3) —
C
Power connection to transfer switch.
D
E ‑ Neutral and/or Ground Connection — Connect to
transfer switch neutral and ground
Series 60000*
Voltage
3 Phase Wye
120/208
3 Phase Wye
139/240
3 Phase Delta
120/240
3 Phase Wye
240/416
277/480
3 Phase Wye
346/600
3 Phase Wye
*Refer to Generator Data Tag to determine series of generator.
D
Rated Amps
Wire Size
215
250 kcmil
186
4/0
186
4/0
108
1 AWG
93
2 AWG
73
4 AWG