Download Print this page

Installing Cables - Huawei NetCol5000-C030 Quick Manual

In-row chilled water smart cooling product
Hide thumbs Also See for NetCol5000-C030:

Advertisement

5

Installing Cables

5.1
Connecting the Equipotential Ground Cable and Power Cable
1. When routing the cables, wrap the section of all signal cables inside the smart cooling
product with the corrugated pipes and route them out of the corresponding cable holes so
that the strong- and weak-current cables are separated.
2. Route the power cable along the rear door post, and use cable ties to secure the cable to the
post every 150–200 mm.
1. Remove the cover of the electric control box.
3. Connect the power cable.
30kW
4. Install the cover of the electric control box.
2. Connect the equipotential cable.
32kW
9

Advertisement

loading

This manual is also suitable for:

Netcol5000-c032