Chapter 2 Replacing the Front Bezel Three Phase UPS unit
Chapter 2 Replacing the Front Bezel Three Phase UPS unit
Overview
This document explains how to replace the UPS unit's front bezel including LDC panel. The
front bezel replacement part number is
Applicable UPS units
Lenovo RT8kVA 6U 3:1 Phase Rack or Tower UPS (380-415VAC), 5594-8PX
•
Lenovo RT11kVA 6U 3:1 Phase Rack or Tower UPS (380-415VAC), 5594-9PX
•
IBM RT8kVA 6U 3:1 Phase Rack or Tower UPS (380-415VAC), 5594-8PX
•
IBM RT11kVA 6U 3:1 Phase Rack or Tower UPS (380-415VAC), 5594-9PX
•
Attention!
A maintenance window for both the Uninterruptible Power Supply (UPS) and the load protected
by this UPS unit must be scheduled when planning to replace the front bezel with the
integrated LCD.
The affected UPS units are to be hard-wired to the utility power. That is no power plugs
Note:
are used to connect the UPS to utility power.
It is not necessary at all to physically disconnect the UPS unit from utility power, that is
to physically disconnect it from the utility power wires.
Connecting and disconnecting the UPS from utility power by hard-wiring and un-wiring
must be done by a licensed and qualifed electrician. This can not be done by a servicer.
Replacing the UPS Front Bezel including LCD
01PE445.
15