Modify Retrofill
Modify AKD-8—AKR30S Switchgear Compartment, Only
• Ensure only qualified personnel install, operate, service, and maintain all electrical
equipment.
EntelliGuard R Circuit Breaker Retrofill AKD-8 Installation Manual
23
WIRING
• Before installing the breaker, the
secondary disconnects must be wired to
the EntelliGuard Breaker.
• Wires with wire markers are provided on
the Retrofill. Make sure that the switchgear
wiring connection points match up with
the original wiring of the cubicle. This
ensures that all wiring connections are
properly made.
•
Wrong connections will cause the breaker
to malfunction.
• It must be ensured that the supply power
to the compartment is turned off/
compartment is de-energized for all the
incoming and outgoing circuits of the LVS
prior to any work being conducted on it.
• During the installation and related work on
the equipment, it must be ensured that the
operator is using the prescribed PPE for the
specified tasks.