3.5 Replacing the Modbus cable assembly
Modbus cable part numbers:
AW503 090 / 1.5 m (4.9 ft.)
AW503 091 / 5 m (16.4 ft.)
AW503 092 / 10 m (32.8 ft.)
AW503 093 / 20 m (65.6 ft.)
Referring to Section 3.2, page 2:
1. Remove the wet-section PCB cover.
Referring to Fig. 3.7:
A
2. Loosen cable gland
and disconnect the Modbus cable
C
connections
marked black, red, screen, green and white.
3. Withdraw the Modbus cable
main case assembly and discard.
4. Feed the replacement Modbus cable into the main case via
E
the guide channel
remake connections to the black, red, screen, green and
white PCB wet-section terminals and at the transmitter.
5. Refit the PCB cover by reversing the removal procedure.
Fig. 3.7 Replacing the Modbus cable assembly
at the wet-section PCB housing
D
from the terminal block
D
from the PCB housing and
at the top, feed through the gland and
B R
SCR
G W
B
For more information please contact:
ABB Limited
Process Automation
Oldends Lane
Stonehouse
Gloucestershire GL10 3TA
UK
Tel:+44 1453 826 661
Fax:+44 1453 829 671
ABB Inc.
Process Automation
125 E. County Line Road
Warminster
PA 18974
USA
Tel:+1 215 674 6000
Fax:+1 215 674 7183
www.abb.com
Note
We reserve the right to make technical changes or modify the contents of this
document without prior notice. With regard to purchase orders, the agreed particulars
shall prevail. ABB does not accept any responsibility whatsoever for potential errors or
possible lack of information in this document.
We reserve all rights in this document and in the subject matter and illustrations
contained therein. Any reproduction, disclosure to third parties or utilization of its
contents in whole or in parts – is forbidden without prior written consent of ABB.
Copyright© 2013 ABB
All rights reserved

Advertisement

loading