PH-5.0L-HDHW Installation Instructions
COMMISSIONING & TESTING
1. Before commissioning, check for debris in the tank. Remove any material which might block the drain line
or drain into the pump tank.
2. Turn on power.
3. Slowly fill the tank with clean water to prime the pump, as the float rises to the On Level position the motor
should turn on.
4. Leave the clean water in the tank as this will effectively prime the pump ready for use.
This pump is designed for use with hot water applications and should be tested annually to ensure it is in full
working order.
MAINTENANCE & SERVICING
1. Before servicing the pump, disconnect the electric power at the fuse box for both the pump and the
equipment unit.
2. It is recommended that the pump be checked every 12 months for proper operation. Most important is to
check for debris blocking the pump non return valve. Check for proper free movement of pump float and
switch.
3. Clean the holding tank and float with warm water and mild soap. Rinse completely when finished.
4. Check the inlet and outlet piping. Clean as necessary.
WARRANTY
This pump offers a 1 year warranty. This warranty covers all parts with material or manufacturing faults. The
buyer's only remedy is the replacement or repair of the defective parts. In no case can labour costs and any
consequential damage be cited as a basis for a complaint. Any returned units must be complete and must
be accompanied by a written list of the defects.
We are unable to accept any liability in case of nonconforming installation or noncompliance with the
specifications or maintenance recommendations.
CONFORMITY
All data contained in these specifications are solely intended to describe the product and do not constitute
warranted characteristics in the legal sense. Subject to technical change.
For further installation advice please call the technical suppo rt helpline on 0115 900 5858.
CE
4
Need help?
Do you have a question about the PH-5.0L-HDHW and is the answer not in the manual?
Questions and answers