4.2
Installing a PE Cable
It is recommended that the PE
cable of the solar inverter be
connected to a nearby ground
point. Connect the PE points
of all solar inverters in the
same array to ensure
equipotential connections to
PE cables.
To enhance the corrosion
resistance of a ground
terminal, you are advised to
apply silica gel or paint on it
after connecting the PE cable.
4.3

Opening the Maintenance Compartment Door

Do not open the panel of the solar inverter.
Before opening the maintenance compartment door, turn off the downstream AC output switch
and three DC switches at the bottom.
Do not open the maintenance compartment door in rainy or snowy days. If you have to, take
protective measures to prevent rain or snow from entering the maintenance compartment.
Do not leave unused screws in the maintenance compartment.
1. Loosen the screws on the
maintenance compartment door.
2. Open the maintenance compartment door and adjust
the support bar.