3 MECHANICAL INSTALLATION

3.1 Siting Requirements – Fig. 3.1
The instrument is designed for wall mounting and weighs approximately 9kg (20lb).
Note. If the flexible conduit supplied with Z-FG2 probes is of insufficient length [6m (20ft.) standard, 10m (33ft.) optional], it
can be extended using a suitable junction box (part no. 003000060) and cables selected from Table 4.1.
Alternatively, cables EXFG/0194 and EXFG/0195 can be used, up to a maximum of 100m (328ft.).
Maximum
100m (330ft.)
A – Close to Oxygen Probe
B – At Eye Level
C – Avoiding Vibration
Caution. Permanent damage
may occur if contaminated
liquid or vapour is allowed to
reach the probe.
D – Avoid Harmful Vapours and Dripping Fluids
4
Probe
Fig. 3.1 Siting Requirements
–5°C
Min.
Note. Analyzer operates to specification between –
20°C and 70°C.
E – Within Temperature Limits
IP66
(NEMA 4x)
F – Within Environmental Limits
55°C
Max.