Chapter 2 Preparations
(1) Installation
Mount the server to a rack in the following procedure.
1. Pull the slide rail from the outer rail until the
slide rail is locked.
2. With two or more persons, firmly hold the
server and mount it to the rack.
3. When the server is pushed into the rack and
is locked, push the server to the end while
pulling the release levers (blue) on both
sides of the server.
4. Push the server until its lock on front panel
clicks.
Important
Always install the server with two or more persons.
Note
Make sure that locking mechanism work normally.
Express5800/R120g-2M User's Guide
Locking mechanism
Locked state