7.2 I
S
NSTALLATION
TEPS
Before installing or maintaining this system, it is extremely important to read this
manual and be sure that all system drawings and schematics are reviewed and
clearly understood. If there are any questions concerning this manual or any of the
installation or maintenance procedures and/or requirements please contact a C&C
Power representative before proceeding.
7.2.1 E
L
QUIPMENT
OCATION
Prior to installation, verify floor loading requirements and all applicable codes pertaining to the
related equipment. Environmental conditions should also be reviewed. Battery systems require
an area with proper ventilation and cooling. An ambient temperature between 20°C to 25°C
(68°F to 77°F) is recommended for optimum battery life and performance. The cabinet has vent
holes located at the front and rear of the system. Never install the cabinet into a sealed
enclosure. Clearance around the equipment should be as suggested by NEC and/or all applicable
national and local codes.
Under certain conditions, batteries can vent potentially explosive gas (hydrogen).
Never enclose batteries or battery cabinets in a sealed room.
7.2.2 E
M
QUIPMENT
OUNTING
Battery cabinet systems are extremely heavy. Use a minimum of two people when
unloading and setting equipment in place.
1. The battery cabinet is equipped with pallet jack or forklift access openings in the front and
rear of the cabinet. Move the equipment into the desired location and set in place.
2. On the floor in the desired location, mark the location of the 6 mounting holes found at the
bottom of the 3 cabinet legs. You may a use the bottom view layout drawing for this;
however the results may not be as accurate.
3. Move the cabinet out of the way and drill holes for the recommended hardware.
4. Move the cabinet back into place, align holes, and tighten hardware.
5. Should any drilling be performed on this equipment, make sure all exposed batteries and
connections are completely covered using insulated type mats.
7.2.3 E
G
QUIPMENT
ROUNDING
All system ground wires should be derived from the main building ground source.
For multi cabinet systems, each cabinet needs to have a designated cabinet ground
wire derived from the main building ground source.
Terminate a cabinet ground wire from the main building ground source to the supplied #6-
300MCM mechanical lug located on the breaker pan. See section 6.2 for sizing recommendations.
Wire should be sized per NEC and/or all applicable national and local codes.
8/27/2013
15
BC39 B
C
ATTERY
ABINET
755-00039 R02