1 Introduction
This publication details cleaning procedures to be performed
before returning an for Aztec piston assembly to the factory for
repair.
Before returning an Aztec piston assembly to the factory,
ensure it has been cleaned and all liquid has been expelled from
the piston chamber. Two options can be used:
— if the piston is
seized, initiate a manual clean (refer to
NOT
Section 4.2, page 5) before removing it for return (refer to
Section 4.3, page 6)
— if the piston is seized a manual clean may not be possible,
remove it from the housing (refer to Section 4.3, page 6)
Follow these guidelines to prevent damage to the piston in
transit and also to comply with the de-contamination
declaration you must sign and return for the repair to be
processed.
Before starting any procedures, read Section 3, page 2.
These procedures must be carried out by a suitably-trained
technician.
2 Tools / Items required
— Operating instruction IM/AZT6CR-EN*
— Medium flat-bladed screwdriver
— Small crosshead screwdriver
*Operating instruction
IM/AZT6CR-EN
via the link (above) or by scanning this code:
can be downloaded

Advertisement

loading

Summary of Contents for ABB Aztec 600

  • Page 1 Service instruction SI/ANAINST/001-EN Aztec 600 Piston assembly Single- and multi-stream colorimetric analyzers Aztec measurement head assembly repairs Measurement made easy 1 Introduction 2 Tools / Items required This publication details cleaning procedures to be performed — Operating instruction IM/AZT6CR-EN* before returning an for Aztec piston assembly to the factory for —...
  • Page 2: Health And Safety

    Products marked with this symbol indicates that the product contains toxic or hazardous substances or elements. The number inside the symbol indicates the environmental protection use period in years. SI/ANAINST/001-EN | Aztec 600 | Piston assembly | Single- and multi-stream colorimetric analyzers...
  • Page 3 Directive as the instructions that should be considered before operating target for all future product design and component the equipment. purchasing. Aztec 600 | Piston assembly | Single- and multi-stream colorimetric analyzers | SI/ANAINST/001-EN...
  • Page 4 The following potential safety hazards are associated with operating the analyzer: — Electrical (line voltage) Fig. 4.1 Isolating the transmitter from incoming mains power supplies — Potentially hazardous chemicals SI/ANAINST/001-EN | Aztec 600 | Piston assembly | Single- and multi-stream colorimetric analyzers...
  • Page 5: Monitor Status

    If this procedure is selected while the analyzer is operating, the following warning is displayed with the Continue option active: To exit press the key, to proceed, press the key. Aztec 600 | Piston assembly | Single- and multi-stream colorimetric analyzers | SI/ANAINST/001-EN...
  • Page 6 6. Remove sample tube end face sealing cap H and remove seal I. Discard the seal. 7. Remove all traces of fluid from the inside of sample tube Fig. 4.5 Removing the measurement cell base plate SI/ANAINST/001-EN | Aztec 600 | Piston assembly | Single- and multi-stream colorimetric analyzers...
  • Page 7 8. Fit the sample tube over the piston assembly and slide it up until it contacts O-ring Z. Fig. 4.8 Removing the motor and sample tube Fig. 4.10 Fitting the piston assembly Aztec 600 | Piston assembly | Single- and multi-stream colorimetric analyzers | SI/ANAINST/001-EN...
  • Page 8 Any reproduction, disclosure to third parties or utilization of its 17. Reconnect measurement cell ribbon cable B. contents in whole or in parts – is forbidden without prior written consent of ABB. Copyright© 2016 ABB All rights reserved...