Installation & Site Survey
2.1
Overview
2.2
Installation & Site Survey Guideline
Tools Required
Line of Sight (LOS)
BroadOne GX4000 Manual (R3.0) issue 1.03
This chapter describes how to install and do the site survey for BroadOne
GX4000 E-band IR system. The main topics covered are;
Installation & Site Survey Guideline
Unpacking the equipment
Preparation of Circuit Breaker for ODU
Antenna fixing to pole
ODU Installation
Cable connection between ODU and external equipment
THE GX4000 EQUIPMENT MUST BE INSTALLED BY SUITABLY
QUALIFIED SERVICE PERSONAL.
THE EQUIPMENT CAN ONLY BE INSTALLED IN A RESTRICTED
To ensure the efficiency of an installation, a proper site survey should be
conducted. Prior to start of an installation, an approved survey team should
conduct a survey of the proposed sites. The team should be approved by the
customer and may consist of either contracted surveyors or employees or
both.
The survey team will need:
A pair of Binoculars
Spotting Scope
GPS Navigation Device
Site Survey Report Form
Equipment Requisition Form
Measure Tape
The 70/80 GHz antenna half beam width is very narrow (less than 1 degree).
This reduces the clearance required between the direct path between sites A
and B and buildings alongside the radio path. The required clearance from
obstacles is called a Fresnel zone.
Fresnel zones are a series of concentric ellipsoid areas surrounding the
straight line path between two antennas.
WARNING
ACCESS LOCATION
Installation