Powering On The System; Power-On Procedure - Huawei SmartLogger2000 Quick Manual

Hide thumbs Also See for SmartLogger2000:
Table of Contents

Advertisement

No.
Check Item
Unused ports (such as RF1, RF2, Ethernet optical port, and
3
Ethernet electrical port) are protected by dustproof plugs.
Routing for the power cable and signal cable meets the
4
requirements for routing strong-current and weak-current cables
and complies with the cable routing plan.
Cables are bound neatly, and cable ties are secured evenly and
5
properly in the same direction.
6
There is no unnecessary adhesive tape or cable tie on cables.
12

Powering On the System

Power-on Procedure

12.1
1. Insert the output terminal of the power adapter into the 12V IN port of the SmartLogger.
2. Insert the power cable into the power adapter.
3. Insert the power cable plug into an AC socket.
NOTE
1. The rated input of the power adapter is 100–240 V AC, 50 Hz or 60 Hz.
2. Select an AC socket that matches the power adapter.
4. Switch on the circuit breaker of the AC socket.
5. Switch on the upstream circuit breaker of the AC power cable.
NOTE
1. Step 5 needs to be performed only in the PLC networking scenario.
2. In a scenario without a smart array controller, place the power adapter on the top of the
SmartLogger and secure the power adapter using a cable tie.
20
Check Result
□ Passed □ Failed
□ Passed □ Failed
□ Passed □ Failed
□ Passed □ Failed

Advertisement

Table of Contents
loading

Table of Contents