Page 4
Copyright This document and parts thereof must not be reproduced or copied without written permission from ABB, and the contents thereof must not be imparted to a third party, nor used for any unauthorized purpose. The software and hardware described in this document is furnished under a license and may be used or disclosed only in accordance with the terms of such license.
Page 5
In case any errors are detected, the reader is kindly requested to notify the manufacturer. Other than under explicit contractual commitments, in no event shall ABB be responsible or liable for any loss or damage resulting from the use of this manual or the application of the equipment.
Page 6
(EMC Directive 2004/108/EC) and concerning electrical equipment for use within specified voltage limits (Low-voltage directive 2006/95/EC). This conformity is the result of tests conducted by ABB in accordance with the product standard EN 60255-26 for the EMC directive, and with the product standards EN 60255-1 and EN 60255-27 for the low voltage directive.
REX060 start up sequence............41 Setting up communication between PCM600 and the IED....41 Writing an application configuration to the IED.........47 Checking CT circuits.................48 Checking VT circuits.................49 Using the RTXP test switch.............. 49 Checking the binary input/output circuits..........50 Generator protection REG670 2.0 IEC Commissioning manual...
Page 8
Entering settings................85 Entering SPA settings..............85 Entering IEC settings..............85 Verifying the communication............86 Verifying SPA communication............. 86 Verifying IEC communication............86 Fibre optic loop................. 87 Optical budget calculation for serial communication with SPA/IEC .87 Generator protection REG670 2.0 IEC Commissioning manual...
Page 9
Verifying the settings............106 Completing the test.............. 107 Generator differential protection GENPDIF ......107 Verifying the settings............107 Completing the test.............. 108 Restricted earth-fault protection, low impedance REFPDIF ..108 Verifying the settings............108 Generator protection REG670 2.0 IEC Commissioning manual...
Page 10
Current protection................148 Instantaneous phase overcurrent protection 3-phase output PHPIOC ..................148 Measuring the operate limit of set values......148 Completing the test.............. 149 Four step phase overcurrent protection 3-phase output OC4PTOC................. 149 Verifying the settings............149 Generator protection REG670 2.0 IEC Commissioning manual...
Page 11
Completing the test.............. 167 Directional overpower protection GOPPDOP ......167 Verifying the settings............167 Completing the test.............. 168 Negative-sequence time overcurrent protection for machines NS2PTOC .................168 Verifying settings by secondary injection......168 Completing the test.............. 170 Generator protection REG670 2.0 IEC Commissioning manual...
Page 12
Verifying settings..............187 Completing the test.............. 188 Frequency protection..............188 Underfrequency protection SAPTUF ........188 Verifying the settings............188 Completing the test.............. 189 Overfrequency protection SAPTOF ..........189 Verifying the settings............189 Completing the test.............. 190 Generator protection REG670 2.0 IEC Commissioning manual...
Page 13
Testing the energizing check..........207 Testing the voltage selection..........209 Completing the test.............. 211 Apparatus control APC.............. 211 Voltage control (VCTR) TR1ATCC, TR8ATCC, TCMYLTC, TCLYLTC...................212 Secondary test..............214 Check the activation of the voltage control operation...214 Generator protection REG670 2.0 IEC Commissioning manual...
Page 14
Function for energy calculation and demand handling ETPMMTR.................231 Verifying the settings............232 Completing the test.............. 233 Station communication..............233 Multiple command and transmit MULTICMDRCV / MULTICMDSND................ 233 Remote communication..............233 Binary signal transfer BinSignReceive, BinSignTransm....233 Generator protection REG670 2.0 IEC Commissioning manual...
Page 15
Determine the cause of an internal failure......247 Self supervision HMI data............247 General IED status............... 247 Fault tracing..................248 Internal fault indications.............248 Using front-connected PC............249 Repair instruction................250 Repair support................252 Maintenance................... 252 Section 16 Glossary............... 253 Generator protection REG670 2.0 IEC Commissioning manual...
The commissioning personnel must have a basic knowledge of handling electronic equipment. The commissioning and maintenance personnel must be well experienced in using protection equipment, test equipment, protection functions and the configured functional logics in the IED. Generator protection REG670 2.0 IEC Commissioning manual...
The manual provides procedures for the checking of external circuitry and energizing the IED, parameter setting and configuration as Generator protection REG670 2.0 IEC Commissioning manual...
The guideline can be used as a technical reference during the engineering phase, installation and commissioning phase, and during normal service. 1.3.2 Dokumentenänderungsverzeichnis Dokument geändert / am Historie -/Mai 2016 Erste Übersetzung von 1MRK 502 053-UEN Version - Generator protection REG670 2.0 IEC Commissioning manual...
The warning icon indicates the presence of a hazard which could result in personal injury. The caution hot surface icon indicates important information or warning about the temperature of product surfaces. Generator protection REG670 2.0 IEC Commissioning manual...
* after an input signal name indicates that the signal must be connected to another function block in the application configuration to achieve a valid application configuration. • Logic diagrams describe the signal logic inside the function block and are bordered by dashed lines. Generator protection REG670 2.0 IEC Commissioning manual...
National and local electrical safety regulations must always be followed. Working in a high voltage environment requires serious approach to avoid human injuries and damage to equipment. Do not touch circuitry during operation. Potentially lethal voltages and currents are present. Generator protection REG670 2.0 IEC Commissioning manual...
Page 32
Take adequate measures to protect the eyes. Never look into the laser beam. The IED with accessories should be mounted in a cubicle in a restricted access area within a power station, substation or industrial or retail environment. Generator protection REG670 2.0 IEC Commissioning manual...
Avoid touching the enclosure of the coupling capacitor REX061 unit and the shunt resistor REX062 unit. The surface may be hot during normal operation. The temperature can rise 50°C in REX061 and 65°C in REX062 above the ambient temperature. Generator protection REG670 2.0 IEC Commissioning manual...
Section 2 1MRK502053-UEN B Safety information Note signs Observe the maximum allowed continuous current for the different current transformer inputs of the IED. See technical data. Generator protection REG670 2.0 IEC Commissioning manual...
APC30 Apparatus control for up to 6 bays, max 30 1-H09 1-H09 1-H09 apparatuses (6CBs) incl. interlocking QCBAY Apparatus control 1+5/APC30 1+5/ 1+5/ 1+5/ APC3 APC3 APC3 Table continues on next page Generator protection REG670 2.0 IEC Commissioning manual...
Page 38
Fuse failure supervision based on voltage 1-G03 1-G03 1-G03 difference Logic SMPPTRC Tripping logic TMAGAPC Trip matrix logic ALMCALH Logic for group alarm WRNCALH Logic for group warning INDCALH Logic for group indication Table continues on next page Generator protection REG670 2.0 IEC Commissioning manual...
Page 39
Elapsed time integrator with limit transgression and overflow supervision Monitoring CVMMXN, Measurements CMMXU, VMMXU, CMSQI, VMSQI, VNMMXU AISVBAS Function block for service value presentation of secondary analog inputs EVENT Event function Table continues on next page Generator protection REG670 2.0 IEC Commissioning manual...
Page 40
I103SUPERV Supervison status for IEC 60870-5-103 I103USRDEF Status for user defiend signals for IEC 60870-5-103 L4UFCNT Event counter with limit supervision Metering PCFCNT Pulse-counter logic ETPMMTR Function for energy calculation and demand handling Generator protection REG670 2.0 IEC Commissioning manual...
GOOSEINTRCV GOOSE function block to receive an integer value GOOSEMVRCV GOOSE function block to receive a measurand value GOOSESPRCV GOOSE function block to receive a single point value Table continues on next page Generator protection REG670 2.0 IEC Commissioning manual...
Page 42
1-P03 redundancy protocol (only in F00) Remote communication Binary signal transfer receive/ 6/36 6/36 6/36 6/36 transmit Transmission of analog data from LDCM Receive binary status from 6/3/3 6/3/3 6/3/3 6/3/3 remote LDCM Generator protection REG670 2.0 IEC Commissioning manual...
Denial of service, frame rate control for OEM port CD DOSSCKT Denial of service, socket flow control GBASVAL Global base values for settings PRIMVAL Primary system values ALTMS Time master supervision ALTIM Time management Table continues on next page Generator protection REG670 2.0 IEC Commissioning manual...
Page 44
IEC 60870-5-103 Optical serial communication RS485103 IEC 60870-5-103 serial communication for RS485 IEC61850-8-1 Parameter setting function for IEC 61850 HORZCOMM Network variables via LON LONSPA SPA communication protocol LEDGEN General LED indication part for LHMI Generator protection REG670 2.0 IEC Commissioning manual...
Circuit diagram • Setting list and configuration • RJ-45 Ethernet cable (CAT 5) • Three-phase test kit or other test equipment depending on the complexity of the configuration and functions to be tested. Generator protection REG670 2.0 IEC Commissioning manual...
To ensure that the IED is according to the delivery and ordering specifications documents delivered together with each IED, the user should also after start-up use the built in HMI to check the IED's: Generator protection REG670 2.0 IEC Commissioning manual...
4.5.1 REX060 start up sequence When the injection unit REX060 is energized, the ABB logotype is shown followed by current REX060 revision status. When the start up sequence is completed, the main menu (normal display content) is shown. The duration of the start up sequence is a few seconds.
Page 48
Tx with Rx on the other side and vice versa. These cables are known as cross over cables. The maximum length is 2 m. The connector type is RJ-45. Generator protection REG670 2.0 IEC Commissioning manual...
Page 49
IED are received on the Tx pin on the PC. Thus, a straight (standard) Ethernet cable can be used. Select Search programs and files in the Start menu in Windows. Generator protection REG670 2.0 IEC Commissioning manual...
Page 50
Section 4 1MRK502053-UEN B Starting up IEC13000057-1-en.vsd IEC13000057 V1 EN Figure 4: Select: Search programs and files Type View network connections and click on the View network connections icon. Generator protection REG670 2.0 IEC Commissioning manual...
Page 51
Right-click and select Properties. IEC13000059-1-en.vsd IEC13000059 V1 EN Figure 6: Right-click Local Area Connection and select Properties Select the TCP/IPv4 protocol from the list of configured components using this connection and click Properties. Generator protection REG670 2.0 IEC Commissioning manual...
Page 52
IP address is not set to be obtained automatically by the IED, see Figure 8. The IP address must be different from the IP address chosen for the IED. Generator protection REG670 2.0 IEC Commissioning manual...
The red LED on the IED flashes, and the green LED is lit while the IED is in the configuration mode. When the configuration is written and completed, the IED is automatically set into normal mode. For further instructions please refer to the users manuals for PCM600. Generator protection REG670 2.0 IEC Commissioning manual...
IED when plotting the excitation characteristics. If the CT secondary circuit earth connection is removed without the current transformer primary being de-energized, dangerous voltages may result in the secondary CT circuits. Generator protection REG670 2.0 IEC Commissioning manual...
IED is in test mode. Before removing the test handle, check the measured values in the IED. Not until the test handle is completely removed, the trip and alarm circuits are restored for operation. Generator protection REG670 2.0 IEC Commissioning manual...
Preferably, disconnect the binary output connector from the binary output cards. Check all connected signals so that both load and polarity are in accordance with IED specifications. 4.12 Checking optical connections Check that the Tx and Rx optical connections are correct. Generator protection REG670 2.0 IEC Commissioning manual...
Page 57
An IED equipped with optical connections has an minimum space requirement of 180 mm for plastic fiber cables and 275 mm for glass fiber cables. Check the allowed minimum bending radius from the optical cable manufacturer. Generator protection REG670 2.0 IEC Commissioning manual...
IED. After that time has elapsed, it will be safe to turn the IED off, no data will be lost. Generator protection REG670 2.0 IEC Commissioning manual...
Take the rated permissive overload values for the current inputs into consideration. Supervision of input/output modules I/O modules configured with PCM600 (BIM, BOM or IOM) are supervised. I/O modules that are not configured are not supervised. Generator protection REG670 2.0 IEC Commissioning manual...
Page 61
Each logical I/O module has an error flag that indicates signal or module failure. The error flag is also set when the physical I/O module of the correct type is not detected in the connected slot. Generator protection REG670 2.0 IEC Commissioning manual...
When the injection is started, check that the injected voltage and current are within the permissible limits. If not, adjust the settings in the injection unit REX060. The ICT tool will check automatically for slight differences between actual injected and set Generator protection REG670 2.0 IEC Commissioning manual...
Page 64
The ICT now makes consecutive measurements until the statistical error reaches an acceptable value. This is graphically shown in a diagram. The user stops the sequence by acceptance of the measurement. The result is stored for later calculations. Generator protection REG670 2.0 IEC Commissioning manual...
Launching injection commissioning tool (ICT) To launch the Injection commissioning tool (ICT), right-click REG670 in the PCM plant structure and select the Injection commissioning. In the ICT toolbar, select the Rotor Earth Fault function. Generator protection REG670 2.0 IEC Commissioning manual...
Page 66
When you are ready to perform calibration, select the Submit and save in report button. ICT will now forward a more accurate frequency to Parameter setting. In Parameter setting, write the newly acquired parameter to IED. Generator protection REG670 2.0 IEC Commissioning manual...
Type 10000 in the real part of the Connected impedance field and leave the imaginary part field empty. This informs the ICT that we have attached 10kΩ pure resistive impedance. In the ICT toolbar, select the Start reading from IED button. Generator protection REG670 2.0 IEC Commissioning manual...
Page 68
12.1. If a failure is indicated during one or more check(s), follow the instructions/tips provided by the ICT in the Calibration result field. 12.2. If these tips do not solve the issue, then contact ABB Support. IEC11000221-1-en.vsd IEC11000221 V1 EN...
Normally continuous readings are performed and the read absolute impedance is viewed in the plot. By observing the standard deviation of the measured impedance, the commissioning engineer can decide if the impedance of the generator is stable/ Generator protection REG670 2.0 IEC Commissioning manual...
Set the graph update period to one second by typing 1 into the Graph update period field. To start continuously plotting values on the graph with one second interval, select Start readings from IED. Generator protection REG670 2.0 IEC Commissioning manual...
Page 71
Trip indication shall be visible in the ICT toolbar. 10. Verify that TRIP and ALARM signals are connected to tripping/alarming/ signaling/communication in accordance with the scheme design. It is very important that the Function Tripping is Enabled under the following situations: Generator protection REG670 2.0 IEC Commissioning manual...
Click the Delete report button in the upper right corner of the auditing screen. • Select a record with the mouse cursor then press the Delete key on the keyboard. Generate logs in one of the following ways: Generator protection REG670 2.0 IEC Commissioning manual...
Right click a graph and select Zoom in or Zoom out in the shortcut menu. IEC11000051-1-en.vsd GUID-3F080E48-8B77-48A0-8283-89511E1AE50B V1 EN Figure 17: Zooming via the shortcut menu • Use the mouse to zoom in and select a part of the graph area. Generator protection REG670 2.0 IEC Commissioning manual...
Select the Browse button. See figure Figure Navigate to a desired folder. Type a suitable file name for the .txt file and select Save. To start logging to this file, select the Start button. Generator protection REG670 2.0 IEC Commissioning manual...
Page 75
1 hour. The period can be adjusted before the logging is started, if needed. The logging can be stopped by selecting the Stop button. You can open the file in notepad or MS Excel. Generator protection REG670 2.0 IEC Commissioning manual...
When the injection is started, check that the injected voltage and current are within the permissible limits. If not, adjust the settings of the injection unit REX060. The ICT tool will check automatically for slight differences between actual injected and set Generator protection REG670 2.0 IEC Commissioning manual...
Page 78
ICT now makes consecutive measurements until the statistical error reaches an acceptable value. This is graphically shown in a Generator protection REG670 2.0 IEC Commissioning manual...
Page 79
ICT also performs verification between the newly acquired and existing reference impedance(s) and warn the user if the resulting estimated fault difference could cause alarm or trip when one reference is shifted from another during operation. Generator protection REG670 2.0 IEC Commissioning manual...
Make sure you have not attached any additional impedance in parallel with the stator circuit. Generator protection REG670 2.0 IEC Commissioning manual...
From the ICT toolbar, select the Start reading from IED button. ICT now performs continuous measurements and after the tenth measurement it starts to update the graph. Notice that the stability region indicator bar reduces in size. Generator protection REG670 2.0 IEC Commissioning manual...
Page 82
12.1. If a failure is indicated during one or more check(s), follow the instructions/tips provided by the ICT in the Calibration result field. 12.2. If these tips do not solve the issue, then contact ABB Support. Generator protection REG670 2.0 IEC...
The injection commissioning tool (ICT) helps the commissioning engineer to acquire additional references for different conditions of the generator. The below description assumes that reference 1 was set during calibration and that a second reference must be set now. Generator protection REG670 2.0 IEC Commissioning manual...
Page 84
2 impedance is presented. Select the Submit to Parameter setting button. This forwards the newly acquired reference to Parameter setting. Write the newly acquired real and imaginary parts of Reference 2 to IED. Generator protection REG670 2.0 IEC Commissioning manual...
Select Fault conductance in the Viewed quantity drop-down menu. The fault conductance is equal to 1/fault resistance, and is more suitable to view when no faults or very small faults are applied/measured. Generator protection REG670 2.0 IEC Commissioning manual...
During installations, calibrations and commissions the ICT generates reports for each of the steps and collects them under the Auditing tab. See the procedures below on how to view and delete reports as well as generate logs from reports. Generator protection REG670 2.0 IEC Commissioning manual...
Page 87
Open and see the details of the file in Notepad or MS Excel. After a successful generation of the log, the system confirms with a message along with the path of the log file. Generator protection REG670 2.0 IEC Commissioning manual...
Use the mouse to zoom in and select a part of the graph area. IEC11000052-1-en.vsd GUID-261171B2-59CD-4248-B873-39A2BC3CD1F1 V1 EN Figure 28: Zooming via area selection of a part of the graph • Press PgUp key on the keyboard to zoom in and PgDn to zoom out. Generator protection REG670 2.0 IEC Commissioning manual...
1 hour. The period can be adjusted before the logging is started, if needed. The logging can be stopped by selecting the Stop button. You can open the file in notepad or MS Excel. Generator protection REG670 2.0 IEC Commissioning manual...
When using the IEC protocol, the rear SPA/IEC port must be set for IEC use. Two types of interfaces can be used: • for plastic fibres with connector type HFBR • for glass fibres with connectors type ST Procedure Generator protection REG670 2.0 IEC Commissioning manual...
SMS/SCS system are as expected. 8.2.2 Verifying IEC communication To verify that the IEC communication with the IEC master system is working, there are some different methods. Choose one of the following. Procedure Generator protection REG670 2.0 IEC Commissioning manual...
Losses in connection box, two contacts (0.5 dB/contact) 1 dB Losses in connection box, two contacts (1 dB/contact) 2 dB Margin for 2 repair splices (0.5 dB/splice) 1 dB Maximum total attenuation 11 dB 7 dB Generator protection REG670 2.0 IEC Commissioning manual...
An optical network can be used within the substation automation system. This enables communication with the IEDs through the LON bus from the operator’s workplace, from the control center and also from other IEDs via bay-to-bay horizontal communication. Generator protection REG670 2.0 IEC Commissioning manual...
Use the LON Network Tool (LNT) to set the LON communication. This is a software tool applied as one node on the LON bus. To communicate via LON, the IEDs need to know Generator protection REG670 2.0 IEC Commissioning manual...
Page 97
Unit Parameter description NeuronID* 0 - 12 Not loaded Neuron hardware identification number in hexadecimal code Location 0 - 6 No value Location of the node *Can be viewed in the local HMI Generator protection REG670 2.0 IEC Commissioning manual...
Losses in connection box, two contacts (0.75 dB/contact) 1.5 dB Losses in connection box, two contacts (1dB/contact) 2 dB Margin for repair splices (0.5 dB/splice) 0.5 dB Maximum total attenuation 11 dB 7 dB Generator protection REG670 2.0 IEC Commissioning manual...
Set Operation to On and PortSelGOOSE to the port used (for example LANAB). Enable redundant IEC 61850-8-1 communication for port AB and CD 2.1. Enable redundant communication. Navigate to: Main menu/Configuration/Communication/Ethernet configuration/PRP:1 Set values for Operation, IPAddress and IPMask. Operation must be set to Generator protection REG670 2.0 IEC Commissioning manual...
LAN-A-STATUS or LAN-B-STATUS (depending on which connection that was removed) are shown as Error and the that other signal is shown as Ok. Be sure to re- connect the removed connection after completed verification. Generator protection REG670 2.0 IEC Commissioning manual...
Prepare the IED for test before testing a particular function. Consider the logic diagram of the tested protection function when performing the test. All included functions in the IED are tested according to the corresponding test instructions in this Generator protection REG670 2.0 IEC Commissioning manual...
IED. To make testing even more effective, use PCM600. PCM600 includes the Signal monitoring tool, which is useful in reading the individual currents and voltages, their Generator protection REG670 2.0 IEC Commissioning manual...
Use the up and down arrows to choose On and press E. Press the left arrow to exit the menu. The dialog box Save changes appears. Choose Yes, press E and exit the menu. Generator protection REG670 2.0 IEC Commissioning manual...
Connect the test equipment according to the IED specific connection diagram and the needed input and output signals for the function under test. An example of a connection is shown in figure 30. Generator protection REG670 2.0 IEC Commissioning manual...
(and the interconnected ones) have the parameters Blocked and eventually EvDisable set to No and Yes respectively. Remember that a function is also blocked if the BLOCK input signal on the corresponding function block is active, Generator protection REG670 2.0 IEC Commissioning manual...
The frequency and active power are located under Main menu/Measurements/ Monitoring/ServiceValues(MMXN)/CVMMXN:x. Then navigate to the bottom of the list to find the frequency. Inject an unsymmetrical three-phase voltage and current, to verify that phases are correctly connected. Generator protection REG670 2.0 IEC Commissioning manual...
Use the disturbance handling tool in PCM600 to evaluate that the protection function has received the correct data and responded correctly (signaling and timing). • Use the event viewer tool in PCM600 to check that only expected events have occurred. Generator protection REG670 2.0 IEC Commissioning manual...
The Manual Trig can be started in two ways: From the local HMI under Main menu/Disturbance records. 1.1. Enter on the row at the bottom of the HMI called Manual trig. Generator protection REG670 2.0 IEC Commissioning manual...
When the IED is brought into normal service it is recommended to delete all events resulting from commissioning tests to avoid confusion in future fault analysis. All events in the IED can be cleared in the local HMI under Main Menu//Clear/Clear Generator protection REG670 2.0 IEC Commissioning manual...
Check in the same way the function by injecting current in phases L2 and L3 respectively. Inject a symmetrical three-phase current and note the operate value. Generator protection REG670 2.0 IEC Commissioning manual...
Note as well that used CT input in the IED must have ratio set as 1:1. This is essential for the measurement of the expected value. Normally Generator protection REG670 2.0 IEC Commissioning manual...
Prepare the IED for verification of settings outlined in section "Requirements" section "Preparing for test" in this chapter. 12.3.3.1 Verifying the settings Go to Main menu/Test/Function test modes/Differential protection and make sure all other functions, configured to the same current transformer inputs Generator protection REG670 2.0 IEC Commissioning manual...
CT in the power transformer neutral-to-earth circuit. Increase the injection current and note the operating value of the protection function. Check that all trip and start contacts operate according to the configuration logic. Generator protection REG670 2.0 IEC Commissioning manual...
To verify the mho characteristic, at least two points should be tested. In the following, three test points are proposed. The mho characteristic always goes through the origin, which automatically gives a fourth point for the characteristic. Generator protection REG670 2.0 IEC Commissioning manual...
The solid line and all test points except 13 are valid for this setting. When operationLdCom parameter is set to Off then the dotted lines and test point 13 are valid. Test points 5, 6, and 7 are not valid for this measurement. Generator protection REG670 2.0 IEC Commissioning manual...
Page 117
–0.2143 x RFPP/2 Exact: 0.8 x RFPP/2 (ArgDir=20°) 0.8 x RFPP/2 –0.4 x RLdFw x tan(ArgDir=20°) 0.4 x RLdFw 0.5 x X1 Exact –0.5 x R1 tan(ArgNegRes=30°) –0.23 x X1 Table continues on next page Generator protection REG670 2.0 IEC Commissioning manual...
Page 118
0.8 x (2 x X1 + X0 0.8 x (2 x R1 + R0 )/3 +RFPE 0.5 x (2 x X1 + R0 0.5 x (2 x R1 )/3 + RFPE Table continues on next page Generator protection REG670 2.0 IEC Commissioning manual...
L3-E according to Figure 32 Table 13 Test points 8 and 9 are intended to test the directional lines of impedance protection. Since directionality is a common Generator protection REG670 2.0 IEC Commissioning manual...
Ensure that the maximum continuous current to the IED does not exceed four times its rated value, if the measurement of the operating characteristics runs under constant voltage conditions. Generator protection REG670 2.0 IEC Commissioning manual...
Page 121
Test points 5, 6, and 7 are not valid for this measurement. 120° R (Ohm/phase) 20° 40% of RLdFw 80% of RLdFw 0.5 x RFPP IEC05000368-3-en IEC05000368 V3 EN Figure 33: Distance protection characteristic with test points for phase-to-phase measurements Generator protection REG670 2.0 IEC Commissioning manual...
Page 122
Exact –0.5 x R1 tan(ArgNegRes=30°) –0.37 x X1 0.5 x X1 0.5 x R1 OperationLdCmp Only used when setting is 0 (Off) 0.5 x RFPP Table is used in conjunction with figure 31. Generator protection REG670 2.0 IEC Commissioning manual...
Page 123
0.85 x RFPE RLdFwset x tan(ArgLdSet) RLdFw RLdFw –02143 x RLdFw Exact: 0.8 x RFPE x tan (ArgDir=20°) 0.8 x RLdFw –0.8 x RLdFw x tan(ArgDir=20°) 0.8 x RLdFw Table continues on next page Generator protection REG670 2.0 IEC Commissioning manual...
(directional angles). Directional functionality testing (trip inside, no-trip outside) should always be carried for all impedance zones set with directionality (forward or reverse). 12.4.3.2 Measuring the operate time of distance protection zones Generator protection REG670 2.0 IEC Commissioning manual...
(IBase). The angle between the voltage and current shall be 0°. With maintained amplitude of the injected voltage the current amplitude and angle is changed to a value ZC/2. Generator protection REG670 2.0 IEC Commissioning manual...
Page 126
0.92 UBase the START signal should be activated. In addition to this the signal ZONE2 should be activated. Set N2Limit to 1 and repeat step 6. Now the signals TRIP2 and TRIP should be activated. Generator protection REG670 2.0 IEC Commissioning manual...
Page 127
Testing functionality by secondary injection Zone 1 Zone 2 X’ Pole slip impedance movement Zone 2 TripAngle Zone 1 WarnAngle IEC07000099_2_en.vsd IEC07000099 V2 EN Figure 35: Setting of the pole slip protection PSPPPAM Generator protection REG670 2.0 IEC Commissioning manual...
If there are several out-of-step relays in the power system, then the one which finds the center of oscillation in its zone 1 should operate first. Generator protection REG670 2.0 IEC Commissioning manual...
The rating of the analogue channels is considered in order to avoid any hardware damage. The test current is lower than the continuous permissive overload current I of the protection current channels of the transformer ovrl module. Generator protection REG670 2.0 IEC Commissioning manual...
Page 130
1; if the test voltage is higher than V , then the test is related to the zone 2. t,RZ1 Considering the resistances and reactances which are related to the settings (ForwardR, ForwardX) and (ReverseR, ReverseX): Generator protection REG670 2.0 IEC Commissioning manual...
Page 131
Limitations may be related to the available test set; the current I was calculated by using a factor 2.5 (instead of the maximum value 4) in order to reduce the magnitude of the test voltage for the points RE and SE. Generator protection REG670 2.0 IEC Commissioning manual...
Page 132
0/0. The accuracy of the impedance reach is ±2% of the base impedance; that is considered while evaluating the test results. Generator protection REG670 2.0 IEC Commissioning manual...
arctan arctan 82. . 14° ∠ = = ForwardR 8 19 (Equation 18) EQUATION14058 V1 EN frequency of V = 50 Hz Generator protection REG670 2.0 IEC Commissioning manual...
Page 134
= = ForwardR 8 19 (Equation 22) EQUATION14058 V1 EN frequency of V = 50 Hz =0 A =0 A • State 2: main test step. Generator protection REG670 2.0 IEC Commissioning manual...
Page 136
= ForwardR 8 19 (Equation 32) EQUATION14058 V1 EN frequency of V = 50 Hz = 0 A = 0 A • State 2: main test step. Generator protection REG670 2.0 IEC Commissioning manual...
Apply the following three-phase symmetrical quantities (the phase angle is related to phase L1): VT s 0 9 5899 38 47 × × × × t RvsZ 13 8 VT p (Equation 57) EQUATION14067 V1 EN Generator protection REG670 2.0 IEC Commissioning manual...
Page 143
Apply the following three-phase symmetrical quantities (the phase angle is related to phase L1): VT s 1 1 5899 47 02 × × × × t RvsZ 13 8 VT p (Equation 67) EQUATION14069 V1 EN Generator protection REG670 2.0 IEC Commissioning manual...
Page 145
= 180º frequency of I = 50.5 Hz Expected result: the protection function does not issue either start or trip. After each test it is possible to download and study the related disturbance recording. Generator protection REG670 2.0 IEC Commissioning manual...
No start or trip signals shall be activated. Feed the IED with current and voltage corresponding to the apparent impedance: Test #2, as shown in figure 39. Read the analog outputs for R and X and check Generator protection REG670 2.0 IEC Commissioning manual...
Page 147
Underexcitation Protection Test #1 Restrain area Test #2 Test #3 Test #4 Z1, Fast zone Z2, Slow zone IEC06000513-2-en.vsd IEC06000513 V2 EN Figure 39: Testing current and voltage corresponding to the apparent impedance Generator protection REG670 2.0 IEC Commissioning manual...
If the measurement of the operating characteristics runs under constant voltage conditions, ensure that the maximum continuous current in an IED does not exceed four times its rated value. To verify the zone 1 mho characteristic, at least two points must be tested. Generator protection REG670 2.0 IEC Commissioning manual...
Page 149
1 has elapsed, the signals TRIP and TRZ1 shall be activated. To verify zone 2 and zone 3 mho characteristic, at least two points must be tested. Generator protection REG670 2.0 IEC Commissioning manual...
Page 150
START and STZx are activated (where x is 2 or 3 depending on selected zone). After the operate time delay of the respective zone has elapsed, also the signals TRIP and TRZx (where x is 2 or 3 depending on selected zone) shall be activated. Generator protection REG670 2.0 IEC Commissioning manual...
ZGVPDIS for the function, or for each individual function in a chain, to be tested next. Remember to set the parameter Blocked to Yes, for each individual function that has been tested. Generator protection REG670 2.0 IEC Commissioning manual...
The injected voltage is fed to a voltage input of the REG670 IED. The current caused by the injection is fed to a current input of the REG670 IED via a current transformer, which is amplifying the current ten times, as shown in figure 42. Generator protection REG670 2.0 IEC Commissioning manual...
Page 153
First the 120 (230) V input to RXTTE4 is disconnected. This should give a signal from REG670 that the injection voltage is low. Reconnect the 120 (230) V input and check that the low injection voltage signal resets. Generator protection REG670 2.0 IEC Commissioning manual...
Inject a phase current into the IED with an initial value below that of the setting. Set the operation mode to 1 out of 3. Increase the injected current in the Ln phase until the TRL (n=1–3) signal appears. Switch the fault current off. Generator protection REG670 2.0 IEC Commissioning manual...
If 2 out of 3 currents for operation is chosen: The voltage angle of phase L1 – the voltage angle of L2 is the reference. If 3 out of 3 currents for operation is chosen: The voltage angle of phase L1 is the reference. Generator protection REG670 2.0 IEC Commissioning manual...
Instantaneous residual overcurrent protection EFPIOC Prepare the IED for verification of settings outlined in section "Requirements" section "Preparing for test" in this chapter. To verify the settings the following fault type should be tested: • Phase-to-earth fault Generator protection REG670 2.0 IEC Commissioning manual...
If the test has been performed by injection of current in phase L1, repeat the test, injecting current into terminals L2 and L3 with a polarizing voltage connected to terminals L2, respectively L3. Block lower set steps when testing higher set steps according to the instructions that follow. Generator protection REG670 2.0 IEC Commissioning manual...
In version 2.0, a typical starting time delay of 24ms is subtracted from the set trip time delay, so that the resulting trip time will take the internal IED start time into consideration. Procedure Generator protection REG670 2.0 IEC Commissioning manual...
Off. Restore connections and settings to their original values, if they were changed for testing purposes. 12.5.6 Sensitive directional residual overcurrent and power protection SDEPSDE Prepare the IED for verification of settings outlined in section "Requirements" section "Preparing for test" in this chapter. Generator protection REG670 2.0 IEC Commissioning manual...
Compare the result with the set value and make sure that the new injected 3I · cos φ is equal to the setting INcosPhi>.. Take the set characteristic into consideration, see Figure and Figure 45. Generator protection REG670 2.0 IEC Commissioning manual...
Page 161
UNRel> . Continue to test another function or complete the test by setting the test mode to Off. RCADir Operate area 3 × ROADir IEC06000650_2_en.vsd IEC06000650 V2 EN Figure 44: Characteristic with ROADir restriction Generator protection REG670 2.0 IEC Commissioning manual...
Page 162
Compare the result with the set value and make sure that the new injected 3I · · cos φ is equal to the setting SN>. Take the set characteristic into consideration, see figure and figure 45. Generator protection REG670 2.0 IEC Commissioning manual...
Page 163
Compare the result with the expected value. The expected value depends on whether definite or inverse time was selected. Continue to test another function or complete the test by setting the test mode to Off. Generator protection REG670 2.0 IEC Commissioning manual...
Page 164
Inject a voltage 0.8 · UNRel> and a current high enough to operate the directional function at the chosen angle. Increase the voltage until the directional function is released. Compare the measured value with the set UNRel> operate value. Generator protection REG670 2.0 IEC Commissioning manual...
With setting Itr = 101%IBase1 and injection current 1.50 · IBase1, the trip time from zero content in the memory shall be 0.60 · Time Constant 1 (Tau1). 12. Check that all trip and alarm contacts operate according to the configuration logic. Generator protection REG670 2.0 IEC Commissioning manual...
Apply the fault condition, including START of CCRBRF, with a current below set IP>. Repeat the fault condition and increase the current in steps until a trip occurs. Compare the result with the set IP>. Disconnect AC and START input signals. Generator protection REG670 2.0 IEC Commissioning manual...
Apply the fault condition, including start of CCRBRF, well above the set current value. Verify that no re-trip, but back-up trip is achieved after set time. RetripMode = CB Pos Check Checking the re-trip with current check, Generator protection REG670 2.0 IEC Commissioning manual...
IP> but above IN>. The residual earth-fault should then be above set IN>. Verify that back-up trip is achieved after set time. If selected, re-trip should also appear. Disconnect AC and START input signals. Generator protection REG670 2.0 IEC Commissioning manual...
Disconnect the start signal(s). Keep the CB closed signal(s). Apply input signal(s), for start of CCRBRF. Arrange disconnection of CB closed signal(s) well before set back-up trip time Verify that back-up trip is not achieved. Generator protection REG670 2.0 IEC Commissioning manual...
Off. Restore connections and settings to their original values, if they were changed for testing purposes. 12.5.9 Pole discordance protection CCPDSC Prepare the IED for verification of settings outlined in section "Requirements" section "Preparing for test" in this chapter. Generator protection REG670 2.0 IEC Commissioning manual...
Completing the test Continue to test another function or end the test by changing the TestMode setting to Off. Restore connections and settings to their original values, if they were changed for testing purposes. Generator protection REG670 2.0 IEC Commissioning manual...
The test is made by means of injection of voltage and current where the amplitude of both current and voltage and the phase angle between the voltage and current can be controlled. During the test the analog outputs of active and reactive power shall be monitored. Generator protection REG670 2.0 IEC Commissioning manual...
In version 2.0, a typical starting time delay of 24ms is subtracted from the set trip time delay, so that the resulting trip time will take the internal IED start time into consideration. 12.5.12.1 Verifying settings by secondary injection Generator protection REG670 2.0 IEC Commissioning manual...
Page 175
This means that if current jumps from 0 to 2 times start and negative sequence capability value of generator K1 is set to 10 s and current start level I2-1> is set Generator protection REG670 2.0 IEC Commissioning manual...
Decrease the current slowly and note the reset value. Connect a trip output contact to a timer. Set the injected current to 200% of the operate level of the tested stage, switch on the current and check the time delay. Generator protection REG670 2.0 IEC Commissioning manual...
− VTprim CTprim UBase × × VTprim (Equation 90) IECEQUATION2433 V1 EN Third part of the characteristic (UHighLimit/100*UBase ≤ Restrain voltage): Generator protection REG670 2.0 IEC Commissioning manual...
Page 178
IL1 is slightly above 0.25 A on the secondary side. The corresponding trip signals TROC and TRIP will be activated after the pre-set time delay has expired. Decrease the current IL1 slowly and note the reset value. Generator protection REG670 2.0 IEC Commissioning manual...
Page 179
Main menu/Settings/IED Settings/Current protection/ VoltageRestOverCurr(51V,2(I>/U<))/VRPVOC(51V,2(I>/U<)):1/ Undervoltage and set the setting Operation_UV = On to activate the undervoltage stage. 13. Slowly decrease the voltage in two phases simultaneously, until the STUV and START signals appear. Generator protection REG670 2.0 IEC Commissioning manual...
The function has heating content memory features. Thus if testing shots are done consecutively, operate time will be shorten accordingly, compared to the given operate characteristic. Therefore either wait until set tReset time has elapsed, between Generator protection REG670 2.0 IEC Commissioning manual...
Precautions if MeasurCurrent = DC. The magnitude of the injected current have to be decreased by multiplying it with a factor of 0.741 in order to get correct operate times when testing with three-phase symmetrical sinusoidal currents. Generator protection REG670 2.0 IEC Commissioning manual...
Prepare the IED for verification of settings outlined in section "Requirements" section "Preparing for test" in this chapter. 12.6.1.1 Verifying the settings Verification of START value and time delay to operate for Step 1 Generator protection REG670 2.0 IEC Commissioning manual...
Page 183
< (Equation 96) IECEQUATION2428 V1 EN where: t(s) Operate time in seconds Settable time multiplier of the function for step 1 Measured voltage U1< Set start voltage for step 1 Generator protection REG670 2.0 IEC Commissioning manual...
UBase × × VTprim (Equation 98) IECEQUATION2427 V1 EN Decrease the voltage slowly and note the reset value. Set and apply about 20% higher voltage than the measured operate value for one phase. Generator protection REG670 2.0 IEC Commissioning manual...
For example, if the inverse time curve A is selected, the trip signals TR1 and TRIP operate after a time corresponding to the equation: − > (Equation 99) IECEQUATION2429 V1 EN Generator protection REG670 2.0 IEC Commissioning manual...
Reduce the voltage slowly and note the reset value. 10. Set the time delay to the correct value according to the setting plan and check the time delay tMin, injecting a voltage corresponding to 1.2 · V/Hz>>. Generator protection REG670 2.0 IEC Commissioning manual...
Apply voltage higher than the highest set value of UDTrip, U1Low and U2Low to the U1 three-phase inputs and to one phase of the U2 inputs according to figure 47. The voltage differential START signal is set. Generator protection REG670 2.0 IEC Commissioning manual...
Page 188
The connections to U1 must be shifted to test another phase. (UL1 to UL2, UL2 to UL3, UL3 to UL1) Check of U2Low Procedure Connect voltages to the IED according to valid connection diagram and figure 48. Generator protection REG670 2.0 IEC Commissioning manual...
Check U2 blocking level by comparing the voltage level at reset with the set undervoltage blocking U2Low. 12.6.5.2 Check of voltage differential trip and alarm levels Procedure Connect voltages to the IED according to valid connection diagram and figure 49. Generator protection REG670 2.0 IEC Commissioning manual...
Observe that the connections to U1 must be shifted to test another phase. (UL1 to UL2, UL2 to UL3, UL3 to UL1) 12.6.5.3 Check of trip and trip reset timers Procdure Generator protection REG670 2.0 IEC Commissioning manual...
Off. Restore connections and settings to their original values, if they were changed for testing purposes. 12.6.6 100% Stator earth fault protection, 3rd harmonic based STEFPHIZ Prepare the IED for verification of settings outlined in section "Requirements" section "Preparing for test" in this chapter. Generator protection REG670 2.0 IEC Commissioning manual...
Read the value of DU (differential voltage). The value of DU should be close to the following value: × × cos(ANGLE) sin(ANGLE) (Equation 101) EQUATION2071 V1 EN Decrease the value of the injected voltage U until the signal START3H is activated. Check that Generator protection REG670 2.0 IEC Commissioning manual...
If the function is used with the option of neutral point measurement only the test is performed by check of this voltage. The operate value should be above the measured residual third-harmonic voltage in the neutral point at normal operation (non-faulted generator). Generator protection REG670 2.0 IEC Commissioning manual...
The test above can be repeated to check the time to reset. The tests above can be repeated to test the frequency dependent inverse time characteristic. Verification of the low voltage magnitude blocking Generator protection REG670 2.0 IEC Commissioning manual...
Note that the measured time consists of the set value for time delay plus minimum operate time of the start function (80 - 90 ms). Extended testing The test above can be repeated to check the time to reset. Generator protection REG670 2.0 IEC Commissioning manual...
Instantaneously decrease the frequency of the applied voltage to a value about 20% lower than the nominal value. Measure the time delay for the TRIP signal, and compare it with the set value. Extended testing Generator protection REG670 2.0 IEC Commissioning manual...
12. Wait for a time corresponding to tCont and ensure that the TRIP and TRIPCONT signals are generated. 13. Measure the time delay for the TRIP signal and compare it to the set value. Generator protection REG670 2.0 IEC Commissioning manual...
Page 198
Ensure that the EnaVoltCheck is enabled. Supply the IED with three-phase currents and voltages at their rated values. Check that the VOLTOK signal appears. Slowly decrease the frequency of the applied voltage until the START signal appears. Generator protection REG670 2.0 IEC Commissioning manual...
Due to the versatile possibilities of CVGAPC itself, but also the possibilities of logic combinations in the application configuration of outputs from more than one CVGAPC function block, it is hardly possible to define a fully covering general commissioning test. Generator protection REG670 2.0 IEC Commissioning manual...
The current restraining value has also to be measured or calculated and the influence on the operation has to be calculated when the testing of the operate value is done. 12.8.1.3 Overcurrent feature with voltage restraint Procedure Generator protection REG670 2.0 IEC Commissioning manual...
Reverse the direction of the injection current and check that the protection does not operate. Check with low polarization voltage that the feature becomes non-directional, blocked or with memory according to the setting. Generator protection REG670 2.0 IEC Commissioning manual...
Inject a current 0.1 · IBase to the reference current input I5. Increase slowly the current in one of the phases current input and check that FAIL output is obtained when the current is about 0.9 · IBase. Generator protection REG670 2.0 IEC Commissioning manual...
There should be no change in the high status of the output signals BLKU and BLKZ. • The signal 3PH will appear. Establish normal voltage and current operating conditions simultaneously and observe the corresponding output signals. They should change to logical 0 as follows: Generator protection REG670 2.0 IEC Commissioning manual...
Observe that the currents in the equation are phasors. × × + × (Equation 108) IECEQUATION00021 V1 EN Where: = the measured phase currents I and I IECEQUATION00020 V1 EN Generator protection REG670 2.0 IEC Commissioning manual...
I and I IECEQUATION00020 V1 EN Compare the result with the set value of the zero-sequence operating current. Consider that the set value 3I0< is in percentage of the base current IBase. Generator protection REG670 2.0 IEC Commissioning manual...
Connect the nominal voltages in all three phases and feed a current below the operate level in all three phases. Keep the current constant. Disconnect the voltage in all three phases simultaneously. The BLKU, BLKZ and 3PH signals should not appear. Generator protection REG670 2.0 IEC Commissioning manual...
Apply three-phase voltages with the value slightly below USealIn level. Decrease one of the three-phase voltages on main fuse group. The voltage change must be greater than the set value for Ud>MainBlock. MAINFUF signal is activated. Generator protection REG670 2.0 IEC Commissioning manual...
The test set must also be able to generate different frequencies on different outputs. The description below applies for a system with a nominal frequency of 50 Hz but can be directly applicable to 60 Hz. SESRSYN can be set Generator protection REG670 2.0 IEC Commissioning manual...
Page 209
Ph/N equipment Ph/Ph Input Phase L1,L2,L3 L12,L23,L31 UMeasure U-Line Ph/N U3PLN1 Ph/Ph Input Phase L1,L2,L3 L12,L23,L31 IEC05000480-4-en.vsd IEC05000480 V4 EN Figure 51: General test connection with three-phase voltage connected to the line side Generator protection REG670 2.0 IEC Commissioning manual...
FreqDiffMin. The test procedure below will depend on the settings used. Input STARTSYN must be activated during the test. FreqDiffMax = 50.2 Hz FreqDiffMin = 50.01 Hz tBreaker = 0.080 s Apply voltages Generator protection REG670 2.0 IEC Commissioning manual...
Increase the U-Bus to 110% GblBaseSelBus, and the U-Line = 90% GblBaseSelLine and also the opposite condition. Check that the two outputs for manual and auto synchronism are not activated. Generator protection REG670 2.0 IEC Commissioning manual...
Page 212
FreqDiffA and FreqDiffM respectively and that operation is blocked when the frequency difference is greater. Test with frequency difference = 0 mHz Test with a frequency difference outside the set limits for manual and auto synchronizing check respectively. Generator protection REG670 2.0 IEC Commissioning manual...
The test should verify that the energizing check function operates for a low voltage on the U-Line and for a high voltage on the U-Bus. This corresponds to the energizing of a dead line to a live bus. Generator protection REG670 2.0 IEC Commissioning manual...
Page 214
Verify the local HMI setting AutoEnerg to be Off and ManEnerg to be DBLL. Set the parameter ManEnergDBDL to On. Apply a single-phase voltage of 30% GblBaseSelBus to the U-Bus and a single- phase voltage of 30% GblBaseSelLine to the U-Line. Generator protection REG670 2.0 IEC Commissioning manual...
SESRSYN 3) functions. These three SESRSYN functions can either be in one, two or three different IEDs. Table describes the scenario when SESRSYN 1, SESRSYN 2 and SESRSYN 3 all are in the same IED. If SESRSYN 3 is in another IED, WA1 will Generator protection REG670 2.0 IEC Commissioning manual...
In such cases, where there is a mismatch, the user is advised to make a complete cycle of block/unblock operations to align the statuses. Generator protection REG670 2.0 IEC Commissioning manual...
Confirm that the setting for short circuit impedance Xr2 for TR1ATCC or TR8ATCC is in accordance with transformer data: • Short circuit impedance, available on the local HMI under Main menu/ Settings/General settings/Control/ Generator protection REG670 2.0 IEC Commissioning manual...
Page 219
Ia, Ib, Ic or the two-phase quantities Ii and Ij, or single-phase current Ii. Also note that for simplicity, the Parameter Setting menu structures included in the following procedure are referred to universally as VCP1, for example, Main menu/Settings/Setting Group N/ Generator protection REG670 2.0 IEC Commissioning manual...
Confirm Transformer Tap Control = On and Transformer Voltage Control = On • Direct tap change control Main menu/Settings/Setting Group N/Control/ TransformerTapChanger(YLTC,84)/TCMYLTC:x/TCLYLTC:x/ Operation • Automatic transformer voltage control Main menu/Settings/Setting Group N/Control/ TransformerVoltageControl(ATCC,90)/TR1ATCC:x/TR8ATCC:x/ General/Operation • Enable Tap Command Generator protection REG670 2.0 IEC Commissioning manual...
Confirm the setting for Ublock, nominally at 80% of rated voltage. Confirm the voltage control function response to an applied voltage below Ublock, by reviewing the setting in the local HMI under Main menu/Settings/ Generator protection REG670 2.0 IEC Commissioning manual...
This situation can also be confirmed through reviewing the disturbance and service reports on the local HMI. Generator protection REG670 2.0 IEC Commissioning manual...
Inject voltage for U equal to setting USet. Inject current equal to rated current I2Base. Confirm on the local HMI that service values for bus voltage and load current are equal to injected quantities. Generator protection REG670 2.0 IEC Commissioning manual...
Review the expected time for first (t1) and subsequent (t2) tap change commands from the master transformer in the local HMI under Main menu/ Generator protection REG670 2.0 IEC Commissioning manual...
Page 225
If T1 - T3 are available, • T1RXOP and T2RXOP shall be set to On in instance 3 of TR8ATCC, • T2RXOP and T3RXOP shall be set to On in instance 1 of TR8ATCC and so on. Generator protection REG670 2.0 IEC Commissioning manual...
Page 226
To cause a tap change, the calculated value for circulating current voltage adjustment must offset the injected quantity for bus voltage U so that Ui is outside the voltage deadband created by setting UDeadband. Expressed by equation and equation 122. Generator protection REG670 2.0 IEC Commissioning manual...
Page 227
Confirm that OperationPAR is set to CC for each transformer in the parallel group. Confirm that OperCCBlock is set to On for each transformer in the parallel group. Review the setting for CircCurrLimit. Generator protection REG670 2.0 IEC Commissioning manual...
12.10.5 Interlocking Prepare the IED for verification of settings outlined in section "Requirements" section "Preparing for test" in this chapter. Generator protection REG670 2.0 IEC Commissioning manual...
In addition to various other tests, the following tests should be performed. They depend on the complete configuration of an IED: Procedure Make sure that TripLockout and AutoLock are both set to Off. Initiate different single-phase-to-earth faults one at a time. Generator protection REG670 2.0 IEC Commissioning manual...
In addition to other tests, the following tests, which depend on the complete configuration of an IED, should be carried out. Procedure Make sure that AutoLock and TripLockout are both set to Off. Initiate different single-phase-to-earth faults one at a time. Generator protection REG670 2.0 IEC Commissioning manual...
Page 231
Check, that the output signals, issued for the first fault, correspond to a two- trip for included phases. The output signals generated by the second fault must correspond to the three-phase tripping action. Generator protection REG670 2.0 IEC Commissioning manual...
Completing the test Continue to test another function or end the test by changing the Test mode setting to Off. Restore connections and settings to their original values, if they were changed for testing purposes. Generator protection REG670 2.0 IEC Commissioning manual...
Off. Restore connections and settings to their original values, if they were changed for testing purposes. 12.12.2 Liquid medium supervision SSIML Prepare the IED for verification of settings as outlined in section "Completing the test" in this chapter. Generator protection REG670 2.0 IEC Commissioning manual...
The Signal Monitoring tool in PCM600 shows the service values that are available on the Local HMI as well. Values of the logical signals belong to the breaker monitoring are available on the local HMI under: Main menu/Test/Function status/Monitoring/ BreakerMonitoring/SSCBR:x Generator protection REG670 2.0 IEC Commissioning manual...
Check that the output CBLIFEPH is decreased with a value that corresponds to the injected current. 6.4. CBLIFEAL is activated as soon as CBLIFEPH is below the set CBLifeAlmLevel value. Test of accumulated energy Generator protection REG670 2.0 IEC Commissioning manual...
Completing the test Continue to test another function or end the test by changing the Test mode setting to Off. Restore connections and settings to their original values if they were changed for testing purposes. Generator protection REG670 2.0 IEC Commissioning manual...
PCM600 or on the local HMI. 12.13.2 Function for energy calculation and demand handling ETPMMTR Prepare the IED for verification of settings as outlined in section ”Overview “ and section ”Preparing for test“ in this chapter. Generator protection REG670 2.0 IEC Commissioning manual...
Check after 1 minute whether the MAXPAFD and MAXPRFD outputs are retaining the old maximum value. Similarly the testing can be done for MAXPAFD and MAXPRFD outputs by changing the power inputs directions through direction settings. Verification of EAFALM & ERFALM outputs Generator protection REG670 2.0 IEC Commissioning manual...
12.15 Remote communication 12.15.1 Binary signal transfer BinSignReceive, BinSignTransm Prepare the IED for verification of settings as outlined in section "Preparing the IED to verify settings". Generator protection REG670 2.0 IEC Commissioning manual...
Page 240
(BO). Check at End2 that the BI signal is received and the BO operates. Repeat the test for all the signals configured to be transmitted over the communication link. Generator protection REG670 2.0 IEC Commissioning manual...
Operating procedures for the PC aided methods of changing the active setting groups are described in the corresponding PCM600 documents and instructions for the operators within the SCS are included in the SCS documentation. Generator protection REG670 2.0 IEC Commissioning manual...
The following procedure is used to return to normal operation. Navigate to the test mode folder. Change the On setting to Off. Press the 'E' key and the left arrow key. Answer YES, press the 'E' key and exit the menus. Generator protection REG670 2.0 IEC Commissioning manual...
ZDMRDIR are available under the HMI menu: Main menu/ Settings/IED Settings/Impedance protection/ DirectionalImpedance The primary load impedance must have an angle (PHI) between the setting angles for the directional lines. In case of default settings this means: Generator protection REG670 2.0 IEC Commissioning manual...
Page 245
(importing) resistive load (active power). Usually it is enough to look at the resistive values to get information of the load direction, that must anyway be compared with the indication given by external equipment measuring the same power flow. Generator protection REG670 2.0 IEC Commissioning manual...
The periodicity of all tests depends on several factors, for example the importance of the installation, environmental conditions, simple or complex equipment, static or electromechanical IEDs, and so on. The normal maintenance praxis of the user should be followed. However, ABB's recommendation is as follows: Every second to third year •...
IED at a time on live circuits where redundant protection is installed and de- energization of the primary circuit is not allowed. ABB protection IEDs are preferably tested by aid of components from the COMBITEST testing system described in information B03-9510 E. Main...
The healthy circuit is of utmost importance for the protection operation. If the circuit is not provided with a continuous trip-circuit supervision, it is possible to check that circuit Generator protection REG670 2.0 IEC Commissioning manual...
The neutral-point voltage to an earth-fault protection IED is checked. The voltage is normally 0.1 to 1V secondary. However, voltage can be considerably higher due to harmonics. Normally a CVT secondary can have around 2.5 - 3% third-harmonic voltage. Generator protection REG670 2.0 IEC Commissioning manual...
Thus a list should be prepared of all items disturbed during test so that all can be put back into service quickly and without overlooking something. It should be put back into service item by item and signed by the responsible engineer. Generator protection REG670 2.0 IEC Commissioning manual...
No problem detected. None. Time synch Fail No time synchronization. Check the synchronization source for problems. If the problem persists, contact your ABB representative for service. Real time clock Ready No problem detected. None. Real time clock Fail The real time clock has Set the clock.
Ready (I/O module name) Fail I/O modules has failed. Check that the I/O module has been configured and connected to the IOP1- block. If the problem persists, contact your ABB representative for service. 15.2 Fault tracing 15.2.1 Internal fault indications...
40 events. The list is based on the FIFO principle, when it is full, the oldest event is overwritten. The list cannot be cleared and its content cannot be erased. Generator protection REG670 2.0 IEC Commissioning manual...
Exact time when the fault occurred. 15.3 Repair instruction Never disconnect the secondary connection of a current transformer circuit without short-circuiting the transformer’s secondary winding. Operating a current transformer with the secondary winding open will Generator protection REG670 2.0 IEC Commissioning manual...
Operation may be disrupted and IED and measuring circuitry may be damaged. An alternative is to open the IED and send only the faulty circuit board to ABB for repair. When a printed circuit board is sent to ABB, it must always be placed in a metallic, ESD-proof, protection bag.
Troubleshooting 15.4 Repair support If an IED needs to be repaired, the whole IED must be removed and sent to an ABB Logistic Center. Before returning the material, an inquiry must be sent to the ABB Logistic Center. e-mail: offer.selog@se.abb.com 15.5...
Binary signal transfer function, receiver blocks Binary signal transfer function, transmit blocks C37.94 IEEE/ANSI protocol used when sending binary signals between IEDs Controller Area Network. ISO standard (ISO 11898) for serial communication Circuit breaker Combined backplane module Generator protection REG670 2.0 IEC Commissioning manual...
Page 260
Delayed autoreclosing DARPA Defense Advanced Research Projects Agency (The US developer of the TCP/IP protocol etc.) DBDL Dead bus dead line DBLL Dead bus live line Direct current Data flow control Discrete Fourier transform Generator protection REG670 2.0 IEC Commissioning manual...
Page 261
Electrical and functional description for digital lines used by local telephone companies. Can be transported over balanced and unbalanced lines Communication interface module with carrier of GPS receiver module Graphical display editor within PCM600 General interrogation command Generator protection REG670 2.0 IEC Commissioning manual...
Page 262
(IEDs) Cyber Security Capabilities Intelligent electronic device I-GIS Intelligent gas-insulated switchgear Binary input/output module Instance When several occurrences of the same function are available in the IED, they are referred to as instances of that Generator protection REG670 2.0 IEC Commissioning manual...
Page 263
Milli-ampere module Main processing module MVAL Value of measurement Multifunction vehicle bus. Standardized serial bus originally developed for use in trains. National Control Centre Number of grid faults Numerical module OCO cycle Open-close-open cycle Generator protection REG670 2.0 IEC Commissioning manual...
Page 264
A balanced serial interface for the transmission of digital data in point-to-point connections RS485 Serial link according to EIA standard RS485 Real-time clock Remote terminal unit Substation Automation Select-before-operate Switch or push button to close Generator protection REG670 2.0 IEC Commissioning manual...
Page 265
TCP/IP is often used to refer to the entire US Department of Defense protocol suite based upon these, including Telnet, FTP, UDP and RDP. Time delayed earth-fault protection function Transport Layer Security Transmit (disturbance data) Generator protection REG670 2.0 IEC Commissioning manual...
Page 266
A digital signalling interface primarily used for telecom equipment Three times zero-sequence current.Often referred to as the residual or the earth-fault current Three times the zero sequence voltage. Often referred to as the residual voltage or the neutral point voltage Generator protection REG670 2.0 IEC Commissioning manual...
Page 268
Contact us Note: For more information please contact: We reserve the right to make technical changes or modify the contents of this document without prior notice. ABB AB ABB AB does not accept any responsibility whatsoever for potential Substation Automation Products errors or possible lack of information in this document.