SICHARGE UC MastHood
5.2 Installation
Example calculation
In the following example calculation, the following values are assumed:
E = 3000 mm
C = 1400 mm (middle of on-board pantograph operating area)
D = C + E
D = 3000 mm + 1400 mm
D = 4400 mm
Lifting the SICHARGE UC MastHood
No.
1
Check the incoming goods with the visual inspection of the overall transport packaging
2
Check that the delivery documents correspond to the goods delivered
3
Loosen the fastening of the transport pallet
4
Attach the approved sling to the end of the mast (see picture below)
5
Place a piece of wood or similar under the base of the mast
6
Lift it carefully until the SICHARGE UC MastHood hangs vertically from the sling
44
Checklist item
Installation and Commissioning Checklist for SICHARGE UC