Hitachi Universal Storage Platform VM Installation Planning Manual page 13

Hide thumbs Also See for Universal Storage Platform VM:
Table of Contents

Advertisement

If any requirements are not met, make the changes required to meet the
requirements. Be sure to allow enough time to complete the required
changes, so your site is ready when the equipment arrives.
4. Provide the customer-supplied hardware required for installation
and configuration (for example, connectors, electrical receptacles, and
rack).
5. Customer-supplied rack: If the Universal Storage Platform VM will be
installed in a customer-supplied rack, review the documentation for the
rack with your Hitachi Data Systems account team to ensure that the
rack meets all applicable requirements.
Installation of the Universal Storage Platform VM in a customer-supplied
rack requires more time than installation in an HDS-supplied rack.
Please allow an additional five hours for installation in a customer-
supplied rack.
6. Work with your Hitachi Data Systems account team during the
installation planning process for the Universal Storage Platform VM.
Planning for Installation
Hitachi Universal Storage Platform VM Installation Planning Guide
1–3