Site-Planning Checklist
Note
Site-Planning Checklist
Table 2-2
Site-Planning Checklist
Task No.
Planning Activity
1
Space evaluation:
Space and layout
•
Floor covering
•
•
Impact and vibration
Lighting
•
Maintenance access
•
2
Environmental evaluation:
Ambient temperature
•
Humidity
•
•
Altitude
Atmospheric contamination
•
Airflow
•
Catalyst 4500 Series Switches Installation Guide
2-16
1 - IEEE class 3 device
total output power 284 W
Total heat dissipated by system = (284/.75) * 3.415 = 1293 BTUs/hr
Although a class 3 device needs 15.4 W to power up, 17.3 W need to be generated
from the backplane in order to have 15.4 W at the switch port. 17.3 W comes from
the WS-X4248-RJ45V DC-DC converter's efficiency (89%).
Table 2-2
lists the site-planning activities that you should complete before you
install a Catalyst 4500 series switch. Completing each activity helps to ensure a
successful switch installation.
Chapter 2
Preparing for Installation
17.3 W
Verified by
Time
Date