100 Series 1U Server Dell EMC VxRack Node Hardware Installation Guide P/N 300-015-513 REV 05...
Page 2
MERCHANTABILITY OR FITNESS FOR A PARTICULAR PURPOSE. USE, COPYING, AND DISTRIBUTION OF ANY DELL SOFTWARE DESCRIBED IN THIS PUBLICATION REQUIRES AN APPLICABLE SOFTWARE LICENSE. Dell, EMC, and other trademarks are trademarks of Dell Inc. or its subsidiaries. Other trademarks may be the property of their respective owners. Published in the USA.
CONTENTS Figures Tables Preface Chapter 1 Before You Begin Conventions used in this document.............12 Where to get help..................12 Site requirements..................13 Hardware acclimation times................ 13 Chapter 2 Installation Guidelines and Cabinet Stack Up Installation in cabinets with single-phase power distribution....... 16 Installation in cabinets with 3-phase delta power distribution.....
Page 4
CONTENTS Management network B, nodes 23 - 32 cabling ......... 56 Chapter 6 Install data network I/O cables Guidelines for installing and connecting data network cables ....60 Data network A, nodes 1 - 16 cabling ............60 Data network A, nodes 17 - 22 cabling ............62 Data network B, nodes 1 - 16 cabling ............
FIGURES Cabinet stack up for a minimum configuration.............17 Cabinet stack up for a maximum configuration............19 Cabinet stack up for a minimum configuration............21 Cabinet stack up for a maximum configuration............23 Cabinet stack up for a minimum configuration............25 Cabinet stack up for a maximum configuration............27 Correct location for ball bearing retainer assembly.............
TABLES Site requirements......................13 Hardware acclimation times (systems and components)..........13 Minimum configuration in single-phase power distribution cabinets......16 Maximum configuration in single-phase power distribution cabinets......17 Minimum configuration in 3-phase delta power distribution cabinets......20 Stack up for a maximum configuration................ 21 Minimum configuration in 3-phase wye power distribution cabinets......
Page 9
Preface As part of an effort to improve its product lines, Dell EMC periodically releases revisions of its software and hardware. Therefore, some functions described in this document might not be supported by all versions of the software or hardware currently in use.
Page 10
EMC products, go to Dell EMC Online Support at https://support.emc.com. Technical support Go to Dell EMC Online Support and click Service Center. You will see several options for contacting Dell EMC Technical Support. Note that to open a service request, you must have a valid support agreement. Contact your Dell EMC sales representative for details about obtaining a valid support agreement or with questions about your account.
CHAPTER 1 Before You Begin This chapter provides information to obtain assistance and to prepare for the installation. Topics include: Conventions used in this document..............12 Where to get help....................12 Site requirements....................13 Hardware acclimation times................13 Before You Begin...
Note To open a service request through the Dell EMC Online Support site, you must have a valid support agreement. Contact your Dell EMC sales representative for details about obtaining a valid support agreement or to answer any questions about your account.
Before You Begin Site requirements Confirm that the customer site meets all requirements before you begin the installation. The following table describes site requirements and provides references to additional information. Table 1 Site requirements Requirement Description Computer room The system requires a properly equipped computer room with controlled temperature and humidity, proper airflow and ventilation, proper power and grounding, system cable routing facilities, and fire equipment.
Page 14
Before You Begin Table 2 Hardware acclimation times (systems and components) (continued) …then let the system or component If the last 24 hours of the acclimate in the new TRANSIT/STORAGE …and the OPERATING environment this many environment was this: environment is this: hours: Nominal 68-72°F Nominal...
CHAPTER 2 Installation Guidelines and Cabinet Stack Up This chapter provides information for equipment installation related to the different types of power distribution within the cabinets. Topics include: Installation in cabinets with single-phase power distribution.......16 Installation in cabinets with 3-phase delta power distribution......
Installation Guidelines and Cabinet Stack Up Installation in cabinets with single-phase power distribution Note Install all the equipment in the cabinet before installing and connecting the power and I/O cables. Install the equipment as described in Equipment Installation on page 29. If you are installing the minimum configuration, refer to Table 3 and Figure 1 for the equipment stack up in the cabinet.
Installation Guidelines and Cabinet Stack Up Figure 1 Cabinet stack up for a minimum configuration Table 4 Maximum configuration in single-phase power distribution cabinets Component Description Quantity Cabinet U Space Function Data Server D51B-1U Server 2 - 17 and 25 - 40 Installation in cabinets with single-phase power distribution...
Page 18
Installation Guidelines and Cabinet Stack Up Table 4 Maximum configuration in single-phase power distribution cabinets (continued) Component Description Quantity Cabinet U Space Function Management Server Kylin 1U Server Management Switch Arista 7010T-48 19 - 20 Data Switch Arista 7050-64 21 - 24 VxRack Node Hardware Installation Guide...
Installation Guidelines and Cabinet Stack Up Figure 2 Cabinet stack up for a maximum configuration Installation in cabinets with 3-phase delta power distribution Installation in cabinets with 3-phase delta power distribution...
Installation Guidelines and Cabinet Stack Up Note Install all the equipment in the cabinet before installing and connecting the power and I/O cables. Install the equipment as described in Equipment Installation on page 29. If you are installing the minimum configuration, refer to Table 5 and Figure 3 for the equipment stack up in the cabinet.
Installation Guidelines and Cabinet Stack Up Figure 3 Cabinet stack up for a minimum configuration Table 6 Stack up for a maximum configuration Component Description Quantity Cabinet U Space Function Data Server D51B-1U Server 2 - 17 and 25 - 34 Installation in cabinets with 3-phase delta power distribution...
Page 22
Installation Guidelines and Cabinet Stack Up Table 6 Stack up for a maximum configuration (continued) Component Description Quantity Cabinet U Space Function Management Server Kylin 1U Server Management Switch Arista 7010T-48 19 - 20 Data Switch Arista 7050-64 21 - 24 VxRack Node Hardware Installation Guide...
Installation Guidelines and Cabinet Stack Up Figure 4 Cabinet stack up for a maximum configuration Installation in cabinets with 3-phase wye power distribution Installation in cabinets with 3-phase wye power distribution...
Installation Guidelines and Cabinet Stack Up Note Install all the equipment in the cabinet before installing and connecting the power and I/O cables. Install the equipment as described in Equipment Installation on page 29. If you are installing the minimum configuration, refer to Table 7 and Figure 5 for the equipment stack up in the cabinet.
Installation Guidelines and Cabinet Stack Up Figure 5 Cabinet stack up for a minimum configuration Table 8 Maximum configuration in 3-phase wye power distribution cabinets Component Description Quantity Cabinet U Space Function Data Server D51B-1U Server 2 - 17 and 25 - 36 Installation in cabinets with 3-phase wye power distribution...
Page 26
Installation Guidelines and Cabinet Stack Up Table 8 Maximum configuration in 3-phase wye power distribution cabinets (continued) Component Description Quantity Cabinet U Space Function Management Server Kylin 1U Server Management Switch Arista 7010T-48 19 - 20 Data Switch Arista 7050-64 21 - 24 VxRack Node Hardware Installation Guide...
Installation Guidelines and Cabinet Stack Up Figure 6 Cabinet stack up for a maximum configuration Installation in cabinets with 3-phase wye power distribution...
Page 28
Installation Guidelines and Cabinet Stack Up VxRack Node Hardware Installation Guide...
CHAPTER 3 Equipment Installation ™ This chapter provides information for installation of the equipment used in a VxRack system. Topics include: Installation of the equipment in the cabinet ............30 Install the D51B-1U server in the cabinet............30 Install the management server in the cabinet.............
Equipment Installation Installation of the equipment in the cabinet Always begin component installation at the bottom of the cabinet and work upward. Install components at the lowest available space for that component type. Placement of the equipment in the cabinet is dependent on the type of power distribution units installed in the cabinet.
Equipment Installation Figure 7 Correct location for ball bearing retainer assembly 7. From the front of the cabinet, align the inner rails attached to the server with the plastic guide block on the front inside of each slide rail. Figure 8 Inner rail over the first part of ball bearing retainer assembly 8.
Equipment Installation Figure 9 Inner rail over the first part of ball bearing retainer assembly 9. Once the inner rails are properly engaged with the ball bearing retainer assemblies, push the server into the cabinet until the slide rails are engaged and locked.
Equipment Installation Table 9 Mounting kit parts (continued) Component Four Phillips pan-head 8-32 x 0.35 in Stabilize the server and rail mounting screws 1U bezel (application specific) Covers front of server in cabinet CL4887 You need a # 2 Phillips-head screwdriver to complete the installation of the rails and server.
Equipment Installation Figure 10 Removing the inner rail from the slide rail CL4883 Attach the inner rails to the server Attach an inner rail to each side of the server by performing the procedure that follows for each rail. Procedure 1.
Page 35
Equipment Installation CL4961 Attach the inner rails to the server...
Equipment Installation Install the server on the rails in the cabinet CAUTION The enclosure is heavy and should be installed into or removed from a rack by two people. To avoid personal injury and/or damage to the equipment, do not attempt to lift and install the enclosure into a rack without a mechanical lift and/or help from another person.
Page 37
Equipment Installation Note For clarity the figure shows the inner rail without the server attached. CL5093 3. Slide the server into the cabinet so the inner rails extends over the plastic guide blocks and the first part of the ball bearing retainer assemblies. Note For clarity the figure shows the inner rail without the server attached.
Equipment Installation CL4962 6. To further secure the rail assembly and server in the cabinet, insert and tighten a small stabilizer screw directly behind each bezel latch. CL4963 Install the management switch in the cabinet Install the management switch in the cabinet There are two cabinet rails (left and right).
Equipment Installation 5. Repeat previous two steps to attach the inner rail to other side of the management switch. 6. Check to ensure that the fan module is oriented with the blue label on left side of fan visible. If not, perform the following: a.
Equipment Installation 11. Type to enter interface configuration mode for the interface management 0 virtual interface which accesses management port 1 on the currently active supervisor. 12. Type , followed by the desired address, to assign a virtual IP ip address address for access to the active management port.
Page 41
Equipment Installation 2. Then, copy usb1:<configuration file>startup-config Example: localhost> enable locathot> copy usbl 3. Type to activate the new configuration. reload This causes the switch to reboot. 4. When prompted, System configuration has been modified. Save?, type 5. When prompted, Proceed with reload?, press enter. 6.
CHAPTER 4 Install AC Power Cables This chapter provides the diagrams and tables for installing and connecting power cables to the power distribution units and the equipment. Topics include: Guidelines for installing and connecting AC power cables ......... 44 Connect AC power cables in cabinets with single-phase power distribution units ...........................46 Connect AC power cables in cabinets with 3-phase delta power distribution units ...........................
Install AC Power Cables Guidelines for installing and connecting AC power cables Use the following illustration as reference for connectors on rear of the servers and switches. VxRack Node Hardware Installation Guide...
Install AC Power Cables Figure 11 Connectors on rear of servers and switches Note As cables are installed and connected, dress and tie cables frequently so that excess slack does not interfere with routing of adjacent cables. Guidelines for installing and connecting AC power cables...
Install AC Power Cables Refer to the diagram that is applicable to the cabinet powder distribution: Single-phase power distribution Connect AC power cables in cabinets with single- phase power distribution units on page 46. 3-phase delta power distribution Connect AC power cables in cabinets with 3- phase delta power distribution units on page 47.
Install AC Power Cables Figure 12 Single-phase power distribution Connect AC power cables in cabinets with 3-phase delta power distribution units Connect AC power cables in cabinets with 3-phase delta power distribution units...
Install AC Power Cables Use Figure 19 to connect power cables in cabinets with 3-phase delta power distribution units. Figure 13 Three-phase delta power distribution VxRack Node Hardware Installation Guide...
Install AC Power Cables Connect AC power cables in cabinets with 3-phase wye power distribution units Use the Figure 20 to connect power cables in cabinets with 3-phase wye power distribution units Connect AC power cables in cabinets with 3-phase wye power distribution units...
CHAPTER 5 Install management network I/O cables This chapter provides the diagrams and tables for installing and connecting cables for the management network. Topics include: Guidelines for installing and connecting management network cables ....52 Management network A, nodes 1 - 16 cabling ............52 Management network A, nodes 17 - 22 cabling ..........
Install management network I/O cables Guidelines for installing and connecting management network cables Use the following illustration as reference for console and management ports on the switches. Figure 15 Console and management ports on switches Note As cables are installed and connected, dress and tie cables frequently so that excess slack does not interfere with routing of adjacent cables.
CHAPTER 6 Install data network I/O cables This chapter provides the diagrams and tables for installing and connecting cables for the data network. Topics include: Guidelines for installing and connecting data network cables ......60 Data network A, nodes 1 - 16 cabling ..............
Install data network I/O cables Guidelines for installing and connecting data network cables Use the following illustration as reference for console and management ports on the switches. Figure 19 Console and management ports on switches Note As cables are installed and connected, dress and tie cables frequently so that excess slack does not interfere with routing of adjacent cables.
Install data network I/O cables Figure 20 Data A, nodes 1 - 16 cabling Table 13 Data A, nodes 1 -16 cabling Source Destination Node1 Port0 Data SwitchA Port 2 Node1 Port1 Data SwitchA Port 4 Node2 Port0 Data SwitchA Port6 Node2 Port1 Data SwitchA Port 8 Node3 Port0...
Install data network I/O cables Figure 21 Data A, nodes 17 - 22 cabling Table 14 Data A, nodes 17 -22 cabling Source Destination Node17 Port0 Data SwitchA Port29 Node17 Port2 Data SwitchA Port31 Node18 Port0 Data SwitchA Port33 Node18 Port2 Data SwitchA Port35 Node19 Port0 Data SwitchA Port37...
Install data network I/O cables Data network B, nodes 1 - 16 cabling Use Figure 28 and Table 15 to connect cables for the data network B, nodes 1 - 16. Figure 22 Data B, nodes 1 - 16 cabling Table 15 Data B, nodes 1 -16 cabling Source Destination...
Install data network I/O cables Table 15 Data B, nodes 1 -16 cabling (continued) Source Destination Node2 Port3 Data SwitchB Port 8 Node3 Port1 Data SwitchB Port 10 Node3 Port3 Data SwitchB Port12 Node4 Port1 Data SwitchB Port14 Node4 Port3 Data SwitchB Port16 Node5 Port1 Data SwitchB Port18...
Install data network I/O cables Data network C, nodes 23 - 32 cabling Use Figure 30 and Table 17 to connect cables for the data network C, nodes 1 - 16. Data network C, nodes 23 - 32 cabling...
CHAPTER 7 Update the Install Database This chapter provides information to update the install database after all installation and configuration work is completed. The chapter contains the following topic: Update the install database................74 Update the Install Database...
After all work is complete, use this procedure to update the install database. Procedure 1. Open a web browser and navigate to the Dell EMC Business Services website at http://emc.force.com/BusinessServices. 2. In the Post Sales area, click Install Base Group.