Figure 4-7 Wall-mounted installation dimensions
Procedure
Step 1 Determine the positions for drilling holes using the marking-off template. Level
the positions of mounting holes using a level, and mark the positions with a
marker.
Step 2 Install the mounting kit.
When drilling holes, avoid the water pipes and power cables buried in the wall.
Issue 07 (2022-01-10)
D ANGER
NO TE
M12x60 expansion bolts delivered with the battery are used to fix the wall mounting
support. If the length and quantity of the bolts do not meet installation requirements,
prepare M12 stainless steel expansion bolts by yourself.
M6x60 expansion bolts delivered with the battery are used to fix the power control module.
If the length and quantity of the bolts do not meet installation requirements, prepare M6
stainless steel expansion bolts by yourself.