ID2000 Series Installation & Commissioning Manual
5.2.1.1 Main Chassis Wiring Connections
3 Connect the 10-way ribbon cable (G) and the power
G
+
-
T E M
P S
N S
R
'A'
4 Ease the connectors of these cables and the ferrite
5 With a sufficient length of each cable pulled through
6 Terminate the cables on the Base PCB - the 10-way
Note: Connector (M) may not be fitted.
7 Fit the chassis into the back box (Section 5.4).
21
cable (H) to the PSU3A. The power cable connects
at two positions, as shown.
through the aperture (I) in the main chassis. Pull the
cables through, taking up any slack.
to connect to the Base PCB, ease the grommet (J)
in to the aperture (I) and then slide it and the cables
sideways into the circular part until secure.
ribbon cable (G) at socket SK18 (K) and the power
cable (H) at socket SK21 (L). Ensure the ferrite is
clear of all circuit boards.
997-433-000-5, Issue 5
May 2010