Commissioning engineer, commissioner / AHJ and customer representative should be satisfied on all aspects of commissioning and
Handover:
agree that the commissioning has met the required codes and standards. The detector must be ready for day to day operation prior to hand over. To
hand over the system to the client obtain the relevant signatures and ensure that all required documents are included.
Hand Over Documents
Copy of this form
Configuration printout or record
(if done) Specific performance test report
Forms required for compliance with local codes and standards
Customer's Signature
Commissioner's Signature
VEA-040-Axx Detector Configuration Record
Use the Xtralis VSC application to print a record of the detector's configuration. Select the detector on the Xtralis VSC tree view at the left and
choose the Print command on the File menu.