28
Installation
I
J
2
K
Smart Meter and LAN connection diagram
PV Array2
When all the connections are inished, check the status in numbering order below.
1) Switch the DC circuit breaker of the connected battery to the 'ON' position.
2) Switch the AC circuit breaker to the 'ON' position.
3) Turn the PV switch of the PCS to the 'ON' position.
Load
1
PV Array1
Strip the additional grounding wire about
15 mm and insert a round terminal into the
wire. And then connect the additional grounding
wire to the additional grounding connector
(mandatory, Torque of 1.5 ± 0.3 N.m)
NOTE
The additional grounding connector must be
connected to the G (Grounding) terminal of
the distribution box correctly. Otherwise the
product could be damaged seriously.
Assemble the lower cover to the product.
And then ix the screws in numbering order.
Fasten the cap of cable gland to ix the cable.
Internet Router
Internet
(Hotspot)
Disconnection
Smart Meter
S/W
Distribution
Box
Load
Load
2
3
Bi-Directional
Power
Meter
Grid