20 | Commissioning (installers only)

4
Commissioning (installers only)
For correct commissioning, it is essential that the
following steps are carried out in the order
shown.
1. Set the DIP switch on IPM 2 in accordance
with the details in the instructions supplied.
2. Switch on the system.
3. Set the DIP switch on FB 100 in accordance
with the details in the instructions supplied.
The functions of the controls and
the meanings of the symbols on the
display are explained on pages 2
and 3.
4. When commissioning for the first time or
after a complete reset (factory reset), you
must select the display language:
– Turn
to select the language and
press
to confirm. (For how to
change the language
page 49.)
5. If the power reserve has run out, set the date
and time as follows:
– Turn
to select the hour and press
to confirm.
– Turn
to select the minute and press
to confirm.
– Turn
to select the year and press
to confirm.
– Turn
to select the month and press
to confirm.
– Turn
to select the day and press
to confirm. (For how to change the
date and time
page 49.)
6. When the unit is first commissioned,
automatic system configuration starts
immediately after entry of the date and time.
– Wait for 60 seconds and then follow the
instructions displayed.
6 720 643 256 (2010/05)
Section 6.4.4 on
Section 6.4.1 on
– If automatic system configuration does
not start of its own accord, start it from
the menu
Section 8.2 on page 66.
7. Adjust other settings to suit the specifics of
the system,
Section 6 starting on page 31
and Section 8 starting on page 57.
8. Fill and bleed the solar heating system
according to its documentation and prepare
it for commissioning as described in
Section 8.4 on page 72.
9. Adjust other settings to suit the specifics of
the solar heating system,
starting on page 73.
10. Commission the solar heating system,
Section 8.5.1 on page 73.
11. Inform the home owner and operator of the
system about its function and method of
operation as follows:
– Explain to the customer how the boiler
and the controls work and how to operate
them.
– Inform the customer about the assigned
heating zones, e.g. heating zone 1 is the
radiator heating and heating zone 2 is the
radiant floor heating.
– Explain to the customer how the system
works, e.g. time, operating modes for the
heating zones, hot water temperature,
time programs for heating zones and hot
water.
– Explain the use of the thermal disinfection
function and the associated risk of
scalding.
– Hand all enclosed documents over to the
user.
12. Complete the commissioning log,
Section 12 on page 98.