Fundamentals

3.1

Requirements for commissioning

The following are necessary for commissioning a SINAMICS S drive system:
● A programming device (PG/PC)
● Startdrive commissioning tool
● A communication interface, e.g. PROFINET, Ethernet
● Completely wired-up drive line-up (see SINAMICS S120 manuals)
A configuration example with booksize components and PROFINET communication is
shown in the following figure:
Figure 3-1
Commissioning with Startdrive
Commissioning Manual, 12/2018, 6SL3097-5AA10-0BP0
Component configuration (example)