2.4.4 Checking Cable Installation

Table 2-16 Checking cable installation
No.
01
02
03
04
05
06
07
08

2.4.5 Checking monitoring device settings

Table 2-17 Checking monitoring device settings
No.
01
02
Issue 07 (2019-12-20)
Check That
Cables are routed properly and meet engineering requirements.
All cable joints are secured properly, especially the cable joints between
network cables and at the cabinet bottom.
Exposed parts near the wiring terminals and lugs are wrapped in PVC
insulation tape or heat shrinking tubing.
All wiring terminals are configured with flat washer, spring washer and
secured properly.
Cables are bundled up neatly, no burr exists, and cable ties are secured
evenly and properly.
Cables are properly routed for ease of convenient maintenance and capacity
expansion.
All labels at the cable ends are clear.
The excess section of a cable strip should be cut evenly.
Check That
The DIP switch is set to 1 for the T/H sensor in the Converged Cabinet.
(Optional) The DIP switch is set to 2 for the T/H sensor in the network
cabinet.
(Optional) The address for the independent deployment AI/DI unit is set to
1.