Preparation for commissioning

Before commissioning observe the conditions described in this chapter.
● The preconditions for commissioning must be fulfilled (in the next chapter).
● The relevant checklist must have been worked through.
● The bus components required for communication must be wired up.
● DRIVE-CliQ wiring rules must be adhered to.
● ON-OFF responses of the drive
1.1

Requirements for commissioning

The following are necessary for commissioning a SINAMICS S drive system:
● STARTER commissioning tool
● An interface, e.g. PROFIBUS, PROFINET, CAN bus or USS (RS232-C)
● Completely wired-up drive line-up (see the Manual)
The following diagram shows a sample configuration with booksize and chassis components.