Electrical installation
4.6 Power connections
4.6.3

Connecting the motor and power cables

Connecting the motor and power cables on the cabinet unit
Note
Position of the connections
For the position of the connections, see the layout diagrams.
1. Open the cabinet, remove the covers (if necessary) in front of the connection panel for
motor cables (terminals U2/T1, V2/T2, W2/T3; X2) and power cables (terminals U1/L1,
V1/L2, W1/L3; X1).
2. Insert the cables through the elastic cable entry below the connection panel.
For example, you can use a knife to make a circular slit to the cable entry at the
appropriate positions and then introduce the cable from below so that a subsequent
sealing is not required.
Figure 4-4
3. Screw the protective earth (PE) into the appropriate terminal (with earth symbol) (50 Nm
for M12) at the points provided in the cabinet.
4. Connect the motor cables to the connections.
Make sure that you connect the conductors in the correct sequence: U2/T1, V2/T2,
W2/T3 and U1/L1, V1/L2, W1/L3!
64
Bottom panel with cable entries with indicated cut-outs
Inverter cabinet units
Operating Instructions, 12/2014, A5E32923362A