Moving Machine By Forklift - Acer Supra 818PD Operation Manual

High precision automatic surface grinder
Hide thumbs Also See for Supra 818PD:
Table of Contents

Advertisement

___________________________________________________________________________ 
4. Shown as figure below, insert the two ends of steel wires through the lifting bolts. Then
place the middle of steel wires at the hook of the hoist (Two steel wires are required).
5. When lifting the machine, using cloth or paper board to isolate at the positions where the
steel wires contact the painted surfaces of the machine.
6. When lifting the packed machine, pay attention to machine leveling and balance.
7. ※During lifting, please always take care of safety!※

3.3 MOVING MACHINE BY FORKLIFT:

3.3.1 MACHINE PACKED BY CRATE:
1. The gravity of the machine is marked on the crate. When lifting the packed machine by
using a forklift, make sure the gravity is located at the center. If you move the machine
from the side, make sure the forks must exceed the gravity by 50cm.
2. The packed machine weight (gross weight) is marked on the crate. Or refer to page 3-2
for machine weight.
3. The loading capacity of the lifting equipment must exceed the weight marked on the crate.
It is suggested to keep lifting height not exceed 12cm from the floor.
3-4
818~2040 PD