Open Stops Adjustments - GE BAKER HUGHES Masoneilan SVi 1000 Quick Start Manual

Table of Contents

Advertisement

Open Stops Adjustments

In some valves the stem travel exceeds the nominal valve travel. The SVi1000 allows you to com-
pensate for this so that the valve position reads 100% at the nominal travel. The acceptable
range is between 60%-100% of possible mechanical travel.
To perform open stops adjustments:
1. Press the upper stop adjustment button for two to seven seconds, until green LED
2 illuminates, then release. Green LED 2 flashes.
2. Move the valve to the desired location via the Open Stop Adjustment Screw
(Figure 21).
Upper Stop
Button and
LED 2
Open Stop
Adjustment
Screw
Cancel
Button and
LED 4
3. Press the upper stop adjustment button for more than two seconds.
The green light goes off, the new stop is saved in the device and the unit is put into
Normal mode.
Press Cancel to abort the process and the green LED 1 goes off, the device returns
to Normal mode and no changes occur.
44 | =BHGE
Figure 21 Open Stop Adjustment Screw
© 2019 Baker Hughes, a GE company, LLC. All rights reserved.