Figure 2.16 Installing Hybrid Cable (4) - Samsung Smart MBS RRH-C2A Installation Manual

Table of Contents

Advertisement

CHAPTER 2. Installation of RRH-C2A
F) Fix the cable to the hoisting wire with a cable tie at regular intervals (within 1 m) to prevent impact or
tension to the upper side of the junction box when lifting the hoist.
Maintain hoisting wire in a straight line, separate the RRH-side cable's curve from the hoisting wire
with 150mm or more distance. And fix cable and wire with cable tie.
(When lifting the hoist, be careful not to apply tension to other areas of the hybrid cable except where
the pulling wire is attached.)
Hybrid Cable
More than 150 mm
Hoisting Wire
2-22

Figure 2.16 Installing Hybrid cable (4)

Pulling Wire
Junction Box
(Breakout Point)
Hoisting Wire
Max. 1 m
Max. 1 m
Max. 1 m