Commissioning with SINUMERIK Operate

11.3.1

Preconditions

For commissioning High Frequency Drive with SINUMERIK Operate, the following preconditions
must be met:
• The High Frequency Drive is connected to an NX module corresponding to the topology rules
(see "DRIVE-CLiQ topology at the HF line-up (Page 164)").
• The High Frequency Drive is commissioned for the first time.
• The control line-up is switched on.
• The drive software is available in version 4.5 or higher.