4-3 Leveling Machine

Set machine by leveling the work table lengthwise and crosswise with engineering
precision levels.

4-4 Handles

When crating, the three ball crank handles are sometimes turned to face the
machine. In this case the handles should be reversed before opera tion.
4-5 Connecting Power S upply
To connect the machine to the plant's power source, please have a qualified
electrician proceed as follows:
1. Check required machine voltage against power source to ensure it is compatible
with the power supply.