ABB PVS-175-TL Quick Installation Manual

Solar inverters 175.0 kw
Hide thumbs Also See for PVS-175-TL:

Advertisement

Quick Links

S O L A R I N V E R T E R S
Quick Installation Guide
PVS-175-TL (175.0 kW)

Advertisement

Table of Contents
loading

Summary of Contents for ABB PVS-175-TL

  • Page 1 — S O L A R I N V E R T E R S Quick Installation Guide PVS-175-TL (175.0 kW)
  • Page 3: Table Of Contents

    — Table of contents 002 – 003 Reference number index Labels and Symbols Models and range of equipment 005 – 007 Lifting and transport List of supplied components 008 – 009 Choice of installation location 010 – 015 Mounting Instructions Routing the cable to the inverter Characteristics of the protective grounding cable...
  • Page 4: Reference Number Index

    17 DC input quick fit connectors 32 AC interface power connector (female) 03 Mounting bracket 18 DC interface connectors (male) 33 Alarm terminal block RS485 ABB service 120Ohm termination res. 04 Handles 19 Logic interface connector (male) (service only) 05 Cover quarter cam locks...
  • Page 5 Wiring Box (internal view) Communication Board...
  • Page 6: Labels And Symbols

    The Communication Identification label is divided in two separate parts by a dashed line; take the bottom part and apply it on the plant documentation. (ABB recommend to create a plant map and apply the Communication Identification label on it).
  • Page 7: Models And Range Of Equipment

    Risk of injury due to the heavy weight of the equipment! ABB usually stores and protects individual components by suitable means to make their transport and subsequent handling easier. Nonetheless, as a rule, it is necessary to turn to the experience of specialised staff to take charge of loading and unloading compo- nents.
  • Page 8 In case of manual lifting the number of required operators necessary to lift the equipment must be in accordance to local regulations relating lifting limits per operator The handles (04) must be mounted into the designated holes located on the enclosures; If lifting with ropes, M12 eyebolts must be mounted in the same holes.
  • Page 9 Always consider the center of gravity of the enclosures while lifting. Center of gravity (wiring box) Center of gravity (power module) PVS-175 In case of manual lifting it’s suggested to use a support plan (e.g. a table) to place the equipment during the lifi- ting operation, to allow the change of hands position.
  • Page 10: List Of Supplied Components

    (for example: the type of surface around the inverter, the general properties of the room, etc.) and the quality of the electricity supply. • All installations over 6500’ (2,000 meters) must be assessed by ABB Technical Sales to determine the proper datasheet derating.
  • Page 11 The minimum clearance distances depends from multiple factor: • Ventilation flow on the top side of the inverter. The upper (A) minimum required free space must be 50 cm. • Possible flooding or damage during grass cutting. It changes the bottom (B) required free space: If the inverter is installed in a place where there are risks of flooding or there is need to cut the grass growing underneath the unit, the bottom (B) minimum recommended free space is 50 cm;...
  • Page 12: Mounting Instructions

    — Mounting Instructions Bracket assembly • Assembly the two side bracket pieces together with the central bracket, by sliding it as shown in the picture and paying atten- tion to the orientation of the pieces (refer to arrow and “UP” markings on the brackets): side brackets arrow have to be turned downwards, central bracket have to be turned upwards.
  • Page 13 • Attach the bracket (03) to the support with at least 6 attachment screws (shown in RED) or at least 6 frame fixing bracket for frame mounting (shown in BLUE). • Depending on the type of anchor chosen, drill the required holes to mount the bracket (03). The pictures shown the recom- mended minimum fixing point depending to the type of support.
  • Page 14 • Insert the two gasket protective covers sliding the positioning pins (shown in red in the picture) into the proper bracket (03) holes. If the mounting is correct the gasket protective cover will have a locked position. • Lift the power module up to the bracket (03) and over the wiring box, using the handles (04) or the M12 eyebolts.
  • Page 15 • Fasten all of the four side closures (latches) (06) as shown it the pictures. Risk of injury due to the heavy weight of the equip- ment. Always consider the center of gravity of the en- closures while lifting. Opening the cover •...
  • Page 16 Final fastening operations In order to reach the four junction screws (20) and complete the power module and wiring box mating, the DC surge arrester plate (21) have to be opened as follow: • Remove the three M5 screws from the DC surge arrester plate (21).
  • Page 17 Connection of the interface connectors Last operation before proceeding with the wiring and connections of AC and DC sources is to connect the five interface connectors that allow the power and communication connection between the power module and the wiring box: •...
  • Page 18: Routing The Cable To The Inverter

    — Routing the cable to the inverter PVS-175 The cable routing have to be done in order to avoid water dripping to the AC panel cable glands (11) (12), DC input quick fit connectors (17) or to ser- vice cable glands (13). 20-30 cm 20-30 cm Min.
  • Page 19: Characteristics Of The Protective Grounding Cable

    2.0 A ABB declares that the ABB transformerless inverters, in terms of their construction, do not inject continuous ground fault currents and therefore there is no requirement that the differential protection installed downstream of the inverter be type B in accordance with IEC 60755 / A 2.
  • Page 20: Output Connection (Ac)

    — Output connection (AC) Before carrying out any operation, check that any external AC switch downstream to the inverter (grid side) are in OFF position and check for voltage absence on the AC conductors! The inverter must be connected to a three-phase TN system with the center of the star connected to ground. To connect the inverter to the grid is necessary to use a three-wire connection (3 phases) without neutral cable.
  • Page 21 Depending on the ground connection method (internal (26) or external (10)) follow the procedures described below: • Internal ground connection: - Pass the protective earth cable trought the proper cable gland (12) on the AC panel. - Fix the protective earth cable lug to the protection earth connection point (int.) (26) using the washers and bolt pre-installed on the M10 stud, as shown in the following installation sequence: Installation sequence:...
  • Page 22: Input Connection (Dc)

    — Input connection (DC) Comply with the maximum input current relating to the quick-fit connectors as indicated in the technical data. The reverse polarity can cause severe damage and electric arc hazards! In case of reverse input strings do not dis- connect them while under load and do not turn the DC disconnect switches (16) to OFF position.
  • Page 23 Decisions on how to structure a photovoltaic system depend on a series of factors and considerations, such as the type of panels, the space availability, the future location of the system, energy production goals over the long term, etc. A configuration program that can help to correctly size the photovoltaic system is available on the ABB website (http://stringsizer. abb.com).
  • Page 24: Connection Of The Communication And Control Signals

    Terminal reference Description of communication and control board (28) Connection to the multifunction relay (ALARM terminal block) RS485 ABB service 120Ohm termination resistance selector switch (ABB service only) DRM0 activation switch RS485 line 120Ohm termination resistance selector switch ABB RS485 service Ethernet connector (RJ45) (ABB service only)
  • Page 25 Internet connection is required to use all the Aurora Vision remote functionalities. Please refer to Aurora Vision documents available on ABB website for further information how to get an Aurora Vi- sion account for remotely monitoring and managing the installed solar assets.
  • Page 26 Configurable Relay connection (ALARM and AUX) The inverter is equipped with 2 multifunction relays terminal blocks (39) with con- figurable activation. It can be connected with normally open contact (being con- nected between the NO terminal and the common contact C) and with normally closed contact (being connected between the NC terminal and the common con- tact C).
  • Page 27: Description Of Led Panel

    ALARM Indicates that the inverter has detected an anomaly. This type of problem is highlighted in the Web User Interface and ABB Installer for Solar Inverters APP. PVS-175 The “GFI” (ground fault) LED indicates that the inverter has detected a ground fault in the DC side photovoltaic generator.
  • Page 28 Pre-commissioning phase (first start-up of inverter) The commissioning of the inverter must be completed through the Installation wizard steps (Web User Interface) or using the ABB Installer for Solar Inverters mobile APP Initial configuration failure The inverter is in locked state due to a failure in the initial configuration of the equipment, such as the standard...
  • Page 29: Commissioning

    Commissioning via ABB Installer for Solar Inverters mobile APP ABB Installer for Solar Inverters APP is available for Android mobile devices with an Android version of 6.0.1 or greater (for iOS mo- bile devices will be implemented soon) and could be downloaded and installed from Play Store.
  • Page 30: Wiring Box

    To address any problems that may occur during the initial stages of operation of the system and to ensure the inverter remains fully functional, you are advised to check for any firmware updates in the download area of the website www.abb.com/solarinver- ters or at https://registration.abbsolarinverters.com (instructions for registering on the website and updating the firmware are...
  • Page 31: Characteristics And Technical Data

    — Characteristics and technical data PVS-175-TL Input Absolute maximum DC input voltage (Vdc, max) 1500 V Start-up DC input voltage (Vstart) 750 V (650...1000 V) Operating DC input voltage range (Vdcmin...Vdcmax) 600 - 1500 V Rated DC input voltage (Vdcr)
  • Page 32: Mounting Bracket

    Modbus RTU/TCP (SunSpec compliant) Commissioning tool Web User Interface, Mobile APP Remote monitoring services Aurora Vision® monitoring portal Embedded logging, direct telemetry data transferring to ABB Advanced features cloud Environmental Ambient temperature range -25...+60°C /-13...140°F with derating above 40°C / 104 °F Relative humidity 4…100 % condensing...
  • Page 33 — For further information For more information on ABB solar products and services, visit www.abb.com/solarinverters...
  • Page 34 — Contact us www.abb.com/solarinverters PVS-175-TL-Quick Installation Guide EN-RevA CC EFFECTIVE 01-02-2019 © Copyright 2019 ABB. All Rights Reserved. Specifications subject to change without notice.

Table of Contents