Table 3-16 Pipeline checklist
Expected Result
All pipes are secured reliably and steadily.
All pipes are wrapped with thermal insulation foam, and the
insulation foam is intact.
The water pipe joints are sealed by sealant.
Check that the needle valve plug is secured (torque of 0.45± 0.05 N
m), and valve bonnet is tightened.
The pipes are not seriously bent.
Issue 02 (2019-10-10)
Copyright © Huawei Technologies Co., Ltd.
3 Installation Guide
Actual Result
□ Passed □ Failed
□ Passed □ Failed
□ Passed □ Failed
□ Passed □ Failed
□ Passed □ Failed