46
Appendix
C Turn off the AC circuit breaker in the distribution box.
And wait at least 10-minute standby period of time to complete discharging this product.
D
E
Disconnect the Ethernet, smart meter, BMS cables from the product.
F
Disconnect the PV1 and PV2 connector from the product.
Disconnect the battery DC cables from the product. Use the appropriate size of a lat-head
G
screwdriver when disconnecting.
H
Disconnect the AC and grounding cable from the product. Use the appropriate size of a screwdriver
when disconnecting.
I
J
5
K
Disassemble the lower cover from the product.
Assemble the lower cover to the product.
And then ix the screws in numbering order.
Remove the screws from the lower wall bracket.
Remove the product from the wall. Make sure that
at least two persons work together to move the
product.