4.
MCB interposing relay settings tested
5.
Safety devices checked and in operation
Motor
1.
Motor installed, aligned and alignment protocol available
2.
Motor decoupled from driven load
3.
Ground connection completed
4.
Customer side motor protection set and ready (e.g. winding temperature, vibration)
5.
Motor auxiliaries (e.g. bearing lubrication, heater cooling) ready
Insulation tests
1.
All power cables to drive, and from drive to motor are meggered, and measured values are
within the required limits.
2.
Test report of the megger test available
Note: If the test is carried out by the commissioning engineer of the drive, an additional day per
drive motor combination needs to be reserved. After the test, the feeder cables can be
connected, except at the drive end. The test must comply with the specification.
3.
Optional insulation tests of the drive are completed and documented. Insulation tests of the
drive recommended in case: long storage time (>4 months), humid environment or visible
damages due to transportation/installation.
Power supply
1.
Medium voltage available for start-up of drive
2.
Low voltage auxiliary power available for start-up of drive
Installation checklist 29