Verifying The Installation; Checking Hardware Installation; Checking Electrical Connections; Checking Cable Installation - Huawei ETP4830-A1 User Manual

Embedded power
Hide thumbs Also See for ETP4830-A1:
Table of Contents

Advertisement

ETP4830-A1 Embedded Power
User Manual

5.1 Checking Hardware Installation

5.2 Checking Electrical Connections

5.3 Checking Cable Installation

Issue 10 (2017-08-08)
5
Check that all screws, especially those used for electrical connections, are secured.
Check that flat washers and spring washers are installed properly.
Check that rectifiers are completely inserted into their respective slots and properly
locked.
Check that all circuit breakers are OFF or all fuses are disconnected.
Check that flat washers and spring washers are securely installed for all OT terminals
and that all the OT terminals are intact and properly connected.
Check that batteries are correctly installed and that battery cables are correctly connected,
and not short circuits exist.
Check that input and output power cables and ground cables are correctly connected, and
not short circuits exist.
Check that all cables are securely connected.
Check that all cables are arranged neatly and bound properly to their nearest cable ties,
and are not twisted or overly bent.
Check that cable labels are properly and securely attached in the same direction.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.

Verifying the Installation

5 Verifying the Installation
30

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents